Exam 12: Project Management
Exam 1: Introduction to Quantitative Analysis63 Questions
Exam 2: Probability Concepts and Applications145 Questions
Exam 3: Decision Analysis119 Questions
Exam 4: Regression Models120 Questions
Exam 5: Forecasting101 Questions
Exam 6: Inventory Control Models113 Questions
Exam 7: Linear Programming Models: Graphical and Computer Methods100 Questions
Exam 8: Linear Programming Applications96 Questions
Exam 9: Transportation and Assignment Models80 Questions
Exam 10: Integer Programming, Goal Programming, and Nonlinear Programming88 Questions
Exam 11: Network Models86 Questions
Exam 12: Project Management123 Questions
Exam 13: Waiting Lines and Queuing Theory Models133 Questions
Exam 14: Simulation Modeling68 Questions
Exam 15: Markov Analysis78 Questions
Exam 16: Statistical Quality Control87 Questions
Select questions type
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity.
(Multiple Choice)
4.9/5
(27)
Your company is considering submitting a bid on a major project. You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies. You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time. What due date should be set?
(Multiple Choice)
4.7/5
(39)
The identification of the project activities and their time, cost, resource requirements, predecessors, and person(s) responsible is called PERT planning.
(True/False)
4.7/5
(28)
Table 12-4
The following represents a project with known activity times. All times are in weeks.
-Using the data in Table 12-4, compute the slack time for activity D.

(Multiple Choice)
4.9/5
(35)
Which of the following statement about project crashing is false?
(Multiple Choice)
4.7/5
(27)
Table 12-6
-What is the variance of Table 12-6's critical path?

(Multiple Choice)
4.7/5
(40)
The expected completion time and variance of an activity is approximated by the normal distribution in a PERT analysis.
(True/False)
4.9/5
(42)
Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks).
(a) What is the project completion date?
(b) What is the total cost required for completing this project on normal time?
(c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?

(Essay)
4.8/5
(41)
The optimistic time is the greatest amount of time that could be required to complete an activity.
(True/False)
4.7/5
(31)
Figure 12-1
-Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project?

(Multiple Choice)
4.9/5
(38)
Given:
Determine:
(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.


(Essay)
4.9/5
(44)
A PERT/CPM network is a graphical display of a project that connects activities.
(True/False)
4.8/5
(33)
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.
(Multiple Choice)
4.9/5
(35)
Figure 12-1
-Given the network shown in Figure 12-1, assume that completion of A is delayed by two days. What other activities are impacted?

(Multiple Choice)
4.8/5
(29)
Table 12-4
The following represents a project with known activity times. All times are in weeks.
-Using the data in Table 12-4, what is the minimum possible time required for completing the project?

(Multiple Choice)
4.7/5
(45)
Showing 61 - 80 of 123
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)