Exam 12: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The critical path of a network is the

(Multiple Choice)
4.9/5
(33)

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity.

(Multiple Choice)
4.9/5
(27)

PERT

(Multiple Choice)
4.8/5
(42)

Your company is considering submitting a bid on a major project. You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies. You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time. What due date should be set?

(Multiple Choice)
4.7/5
(39)

The identification of the project activities and their time, cost, resource requirements, predecessors, and person(s) responsible is called PERT planning.

(True/False)
4.7/5
(28)

Table 12-4 The following represents a project with known activity times. All times are in weeks. Table 12-4 The following represents a project with known activity times. All times are in weeks.   -Using the data in Table 12-4, compute the slack time for activity D. -Using the data in Table 12-4, compute the slack time for activity D.

(Multiple Choice)
4.9/5
(35)

Which of the following statement about project crashing is false?

(Multiple Choice)
4.7/5
(27)

Table 12-6 Table 12-6   -What is the variance of Table 12-6's critical path? -What is the variance of Table 12-6's critical path?

(Multiple Choice)
4.7/5
(40)

The expected completion time and variance of an activity is approximated by the normal distribution in a PERT analysis.

(True/False)
4.9/5
(42)

Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks).   (a) What is the project completion date? (b) What is the total cost required for completing this project on normal time? (c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost? (a) What is the project completion date? (b) What is the total cost required for completing this project on normal time? (c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?

(Essay)
4.8/5
(41)

The optimistic time is the greatest amount of time that could be required to complete an activity.

(True/False)
4.7/5
(31)

Which of the following questions can be answered by PERT?

(Multiple Choice)
4.9/5
(33)

Figure 12-1 Figure 12-1   -Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project? -Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project?

(Multiple Choice)
4.9/5
(38)

The crash time of an activity represents

(Multiple Choice)
4.8/5
(37)

Given: Given:     Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Given:     Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks.

(Essay)
4.9/5
(44)

A PERT/CPM network is a graphical display of a project that connects activities.

(True/False)
4.8/5
(33)

In PERT, we assume that

(Multiple Choice)
4.9/5
(37)

Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.

(Multiple Choice)
4.9/5
(35)

Figure 12-1 Figure 12-1   -Given the network shown in Figure 12-1, assume that completion of A is delayed by two days. What other activities are impacted? -Given the network shown in Figure 12-1, assume that completion of A is delayed by two days. What other activities are impacted?

(Multiple Choice)
4.8/5
(29)

Table 12-4 The following represents a project with known activity times. All times are in weeks. Table 12-4 The following represents a project with known activity times. All times are in weeks.   -Using the data in Table 12-4, what is the minimum possible time required for completing the project? -Using the data in Table 12-4, what is the minimum possible time required for completing the project?

(Multiple Choice)
4.7/5
(45)
Showing 61 - 80 of 123
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)