Exam 12: Project Management
Exam 1: Introduction to Quantitative Analysis63 Questions
Exam 2: Probability Concepts and Applications145 Questions
Exam 3: Decision Analysis119 Questions
Exam 4: Regression Models120 Questions
Exam 5: Forecasting101 Questions
Exam 6: Inventory Control Models113 Questions
Exam 7: Linear Programming Models: Graphical and Computer Methods100 Questions
Exam 8: Linear Programming Applications96 Questions
Exam 9: Transportation and Assignment Models80 Questions
Exam 10: Integer Programming, Goal Programming, and Nonlinear Programming88 Questions
Exam 11: Network Models86 Questions
Exam 12: Project Management123 Questions
Exam 13: Waiting Lines and Queuing Theory Models133 Questions
Exam 14: Simulation Modeling68 Questions
Exam 15: Markov Analysis78 Questions
Exam 16: Statistical Quality Control87 Questions
Select questions type
In PERT, the variance in completion time is equal to the variance of the most time consuming activity on the critical path.
(True/False)
4.8/5
(32)
In a PERT network, the earliest (activity) start time is the
(Multiple Choice)
4.7/5
(32)
CPM was developed for use in managing projects about which we have good information about activity or task completion times.
(True/False)
4.9/5
(33)
PERT is a network technique similar to CPM, but PERT allows for project crashing, whereas CPM does not.
(True/False)
4.8/5
(34)
Table 12-2
The following represents a project with four activities. All times are in weeks.
-According to the data in Table 12-2, what is the minimum expected completion time for the project?

(Multiple Choice)
4.9/5
(35)
PERT is a deterministic analysis tool allowing for precise times of activities within a project.
(True/False)
4.9/5
(39)
PERT was developed for a project for which activity or task times were uncertain.
(True/False)
4.8/5
(45)
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.
(Multiple Choice)
4.9/5
(33)
Table 12-4
The following represents a project with known activity times. All times are in weeks.
-Using the data in Table 12-4, compute the latest finish time for activity E.

(Multiple Choice)
4.7/5
(38)
Consider the tasks, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow.
(a) What is the expected duration of the project?
(b) What is the probability of completion of the project before week 42?

(Essay)
5.0/5
(40)
Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks).
(a) If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed, and how much will this increase the total cost?
(b) What would be the added cost if you wanted to complete the project in the minimum time possible?

(Essay)
4.8/5
(39)
With PERT, we are able to calculate the probability of finishing the project within a specified time.
(True/False)
4.9/5
(35)
Table 12-1
The following represents a project with know activity times. All times are in weeks.
-Using the data in Table 12-1, what is the minimum possible time required for completing the project?

(Multiple Choice)
4.9/5
(23)
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity.
(Multiple Choice)
4.9/5
(33)
Table 12-1
The following represents a project with know activity times. All times are in weeks.
-Using the data in Table 12-1, compute the latest finish time for activity E.

(Multiple Choice)
4.8/5
(38)
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.
(Multiple Choice)
4.8/5
(31)
What is the minimum possible time required for completing the Table 12-5 project?
(Multiple Choice)
4.8/5
(36)
Showing 101 - 120 of 123
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)