Exam 7: Determining Costs, Budget and Earned Value

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If the project has a negative cost variance, then

(Multiple Choice)
4.8/5
(34)

The cumulative budgeted cost is

(Multiple Choice)
4.8/5
(44)

The project cost estimate is allocated to

(Multiple Choice)
4.8/5
(42)

The ____ is a measure of the cost efficiency with which the project is being performed.

(Multiple Choice)
4.8/5
(32)

It is important to manage the cash flow on a project.

(True/False)
4.8/5
(32)

When evaluating work packages that have a negative cost variance, you should focus on taking corrective actions to reduce the costs of:

(Multiple Choice)
4.9/5
(37)

The positive cost variance means

(Multiple Choice)
4.7/5
(31)

When the budgets for all the work packages are summed,

(Multiple Choice)
4.8/5
(35)

Costs related to ____ are for outsourced work when the project teams or contractors do not have the expertise or resources to do certain project tasks.

(Multiple Choice)
4.7/5
(35)

____ is the value of the work actually performed, and is a key parameter that must be determined throughout the project.

(Multiple Choice)
4.9/5
(40)

A third method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost.If the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then

(Multiple Choice)
4.8/5
(40)

Calculate the forecasted cost at completion if the cumulative actual cost is $10,000 and the re-estimate of remaining work to be performed is $5,000.

(Multiple Choice)
4.9/5
(31)

The earned value is

(Multiple Choice)
4.8/5
(36)

There are two approaches to establishing the total budgeted cost for each work package:

(Multiple Choice)
4.9/5
(29)

The cumulative earned value for each work package is calculated by multiplying each percent complete by the ____ for the work package.

(Multiple Choice)
4.8/5
(37)

Earned value, the value of ____, is a key parameter that must be determined throughout the project.

(Multiple Choice)
4.9/5
(36)

Travel costs in the project costs estimate are for

(Multiple Choice)
4.7/5
(29)

The forecasted cost at completion is

(Multiple Choice)
4.7/5
(36)

The key to effective cost control is waiting to address negative cost variances and cost inefficiencies after they are identified.

(True/False)
4.9/5
(38)

The ____ is the amount that is budgeted to accomplish the work that was scheduled to be performed up to a certain point in time

(Multiple Choice)
4.9/5
(44)
Showing 21 - 40 of 103
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)