Exam 7: Determining Costs, Budget and Earned Value
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
The ____ is a measure of the cost efficiency with which the project is being performed.
(Multiple Choice)
4.8/5
(32)
When evaluating work packages that have a negative cost variance, you should focus on taking corrective actions to reduce the costs of:
(Multiple Choice)
4.9/5
(37)
Costs related to ____ are for outsourced work when the project teams or contractors do not have the expertise or resources to do certain project tasks.
(Multiple Choice)
4.7/5
(35)
____ is the value of the work actually performed, and is a key parameter that must be determined throughout the project.
(Multiple Choice)
4.9/5
(40)
A third method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost.If the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then
(Multiple Choice)
4.8/5
(40)
Calculate the forecasted cost at completion if the cumulative actual cost is $10,000 and the re-estimate of remaining work to be performed is $5,000.
(Multiple Choice)
4.9/5
(31)
There are two approaches to establishing the total budgeted cost for each work package:
(Multiple Choice)
4.9/5
(29)
The cumulative earned value for each work package is calculated by multiplying each percent complete by the ____ for the work package.
(Multiple Choice)
4.8/5
(37)
Earned value, the value of ____, is a key parameter that must be determined throughout the project.
(Multiple Choice)
4.9/5
(36)
The key to effective cost control is waiting to address negative cost variances and cost inefficiencies after they are identified.
(True/False)
4.9/5
(38)
The ____ is the amount that is budgeted to accomplish the work that was scheduled to be performed up to a certain point in time
(Multiple Choice)
4.9/5
(44)
Showing 21 - 40 of 103
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)