Exam 7: Determining Costs, Budget and Earned Value

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Committed costs in a project are

(Multiple Choice)
4.9/5
(34)

If the cumulative earned value is $10 and the cumulative actual costs are $20, then the CPI is

(Multiple Choice)
4.8/5
(37)

Cost estimates should be unreasonable and excessive.

(True/False)
4.9/5
(42)

In many projects, large dollar amounts are expended for materials or services (subcontractors, consultants)that are used over a period of time longer than one cost reporting period.

(True/False)
4.9/5
(43)

Often, the sum of the initial estimated costs is greater than the amount of funds budgeted by the sponsor.What should be done to arrive at an acceptable budget amount?

(Multiple Choice)
4.8/5
(36)

The to-complete performance index is

(Multiple Choice)
4.9/5
(29)

The actual cost on a project is

(Multiple Choice)
4.8/5
(38)

A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget.If the cumulative actual cost is greater than the cumulative earned value, then

(Multiple Choice)
4.8/5
(39)

The ____ is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time.

(Multiple Choice)
4.8/5
(41)

To keep track of ____, it's necessary to set up a system to collect, on a regular and timely basis, data on funds actually expended.

(Multiple Choice)
4.8/5
(37)

Costs are ____ when an item is ordered even though actual payment may take place at some later time.

(Multiple Choice)
4.7/5
(38)

Allocating total project costs for the various elements to the appropriate work packages will establish

(Multiple Choice)
4.9/5
(35)

The percent complete estimate for a work package is subjective and requires an underestimated guess compared to the scope of the work package.

(True/False)
4.8/5
(41)

The ____ is the amount that was actually spent to accomplish the work that was scheduled to be performed up to that point in time.

(Multiple Choice)
4.8/5
(38)

The budget for each work package is

(Multiple Choice)
4.7/5
(32)

The cumulative earned value of the project is

(Multiple Choice)
4.8/5
(30)

Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to

(Multiple Choice)
4.8/5
(37)

The ____ is the product of the percent complete and the sum of the estimated costs of all the specific activities that make up a work package or the project.

(Multiple Choice)
4.8/5
(34)

Facilities costs in the project costs estimate are for

(Multiple Choice)
4.8/5
(39)

What is the cost performance index for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000.

(Multiple Choice)
4.8/5
(32)
Showing 41 - 60 of 103
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)