Exam 7: Determining Costs, Budget and Earned Value

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The contractor's outflow of cash can be controlled by

(Multiple Choice)
4.9/5
(38)

The key to managing cash flow is to ensure that cash comes in faster than it goes out.

(True/False)
4.8/5
(30)

Based on analysis of actual cost it is possible to forecast what the total costs will be at the completion of the project or work package.

(True/False)
4.8/5
(36)

Calculate the cost variance if the cumulative earned value is $10 and the cumulative actual costs are $20.

(Multiple Choice)
4.7/5
(38)

The estimated cost of an activity should be

(Multiple Choice)
4.9/5
(38)

The total project cost is often estimated during the ____ phase of the project or when the project charter or a proposal is prepared

(Multiple Choice)
5.0/5
(29)

It is good practice to have the person who will be responsible for the costs associated with the work make the cost estimates.

(True/False)
4.9/5
(40)

It may be easier to estimate the costs for ____, but as the project progresses, the project team can progressively elaborate the estimated costs as more information is known or becomes clear to allow for more accurate estimated costs.

(Multiple Choice)
4.8/5
(31)

Committed costs need to be treated in a special way so that the system

(Multiple Choice)
4.7/5
(45)

Determining the earned value involves collecting data on the percent complete for each work package and then converting this percentage to a dollar amount by multiplying the ____ of the work package by the percent complete.

(Multiple Choice)
4.9/5
(32)

As data are collected on ____, including portions of any committed cost, they need to be totaled by work package so that they can be compared to the ____

(Multiple Choice)
4.7/5
(46)

The cost performance index (CPI)is a measure of the cost efficiency with which the project is being performed.If the cumulative earned value is greater than the cumulative actual costs, then

(Multiple Choice)
4.8/5
(34)

In many cases, there will be a tradeoff, reducing cost variances will involve a reduction in project scope or a delay in the project schedule.

(True/False)
4.8/5
(36)

The first method for determining ____ assumes that the work to be performed on the remaining portion of the project or work package will be done at the same rate of efficiency as the work performed so far.

(Multiple Choice)
4.9/5
(34)

Cumulative actual cost (CAC)should be calculated to compare to the cumulative budgeted cost (CBC).

(True/False)
4.8/5
(42)

Calculate the forecasted cost at completion if the total budgeted cost is $15,000, the cumulative actual cost is $10,000, and the cumulative earned value is $12,000.

(Multiple Choice)
4.9/5
(42)

It is important to use the ____ as the standard against which actual cost is compared.

(Multiple Choice)
4.8/5
(44)

Consider a project that involves painting five similar houses over ten weeks (one house every two weeks)for a total budgeted cost of $20,000.The budget is $4,000 per house.At of the end of week 5, you determine that $10,000 has actually been spent and three houses have been painted completely. What is the earned value of the project?

(Multiple Choice)
4.8/5
(39)

The cumulative actual costs of a project include

(Multiple Choice)
4.9/5
(33)

Equipment costs in the project costs estimate are for equipment

(Multiple Choice)
4.8/5
(30)
Showing 81 - 100 of 103
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)