Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
You must know the mean of an activity in order to determine its standard deviation.
(True/False)
4.9/5
(40)
An activity has an optimistic time estimate of 15 days, a most likely estimate of 24 days, and a pessimistic estimate of 40 days. What is the variance of the activity?
(Multiple Choice)
4.8/5
(42)
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. 

(Multiple Choice)
4.9/5
(35)
In order to reduce the length of a project, it would be wise to shorten:
(Multiple Choice)
4.8/5
(36)
These can be located by doing a backward pass through a network.
(Multiple Choice)
4.9/5
(43)
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.9/5
(36)
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. 

(Multiple Choice)
4.9/5
(40)
Use the information in the table to determine the late start time for Activity E. 

(Multiple Choice)
4.8/5
(34)
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity? 

(Multiple Choice)
4.9/5
(39)
Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity? 

(Multiple Choice)
4.8/5
(32)
Ray's shipment of materials hit every red light and traffic jam on the way to the site. Upon arrival, half of the material was judged defective, necessitating a trip back to the supplier, and then the same arduous journey back to the site once the new materials were loaded. Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip. In the final analysis:
(Multiple Choice)
4.8/5
(33)
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
(True/False)
4.9/5
(38)
Activities C, D, and E in the project represented by the network are to be hammocked. What are the late start and early finish times of the hammock activity? 

(Multiple Choice)
4.9/5
(29)
__________ activities have two or more immediate predecessors.
(Short Answer)
4.8/5
(47)
__________ activities can be used as summaries for some subsets of the activities identified in the overall project network.
(Short Answer)
4.8/5
(40)
Preceding activities are those that must occur before others can be done.
(True/False)
4.9/5
(40)
Showing 41 - 60 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)