Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

You must know the mean of an activity in order to determine its standard deviation.

(True/False)
4.9/5
(40)

An activity has an optimistic time estimate of 15 days, a most likely estimate of 24 days, and a pessimistic estimate of 40 days. What is the variance of the activity?

(Multiple Choice)
4.8/5
(42)

Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.

(Multiple Choice)
4.9/5
(35)

In order to reduce the length of a project, it would be wise to shorten:

(Multiple Choice)
4.8/5
(36)

These can be located by doing a backward pass through a network.

(Multiple Choice)
4.9/5
(43)

What is the slack time for Activity B given the activity times and precedence requirements shown in the table? What is the slack time for Activity B given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.9/5
(36)

Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

(Multiple Choice)
4.9/5
(40)

What is the slack time for activity E? What is the slack time for activity E?

(Multiple Choice)
4.9/5
(35)

Use the information in the table to determine the late start time for Activity E. Use the information in the table to determine the late start time for Activity E.

(Multiple Choice)
4.8/5
(34)

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?

(Multiple Choice)
4.9/5
(39)

A project's duration can be reduced by:

(Multiple Choice)
4.9/5
(43)

In general, the better candidates for shortening are:

(Multiple Choice)
4.9/5
(34)

Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity? Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity?

(Multiple Choice)
4.8/5
(32)

Ray's shipment of materials hit every red light and traffic jam on the way to the site. Upon arrival, half of the material was judged defective, necessitating a trip back to the supplier, and then the same arduous journey back to the site once the new materials were loaded. Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip. In the final analysis:

(Multiple Choice)
4.8/5
(33)

Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.

(True/False)
4.9/5
(38)

Activities C, D, and E in the project represented by the network are to be hammocked. What are the late start and early finish times of the hammock activity? Activities C, D, and E in the project represented by the network are to be hammocked. What are the late start and early finish times of the hammock activity?

(Multiple Choice)
4.9/5
(29)

__________ activities have two or more immediate predecessors.

(Short Answer)
4.8/5
(47)

__________ activities can be used as summaries for some subsets of the activities identified in the overall project network.

(Short Answer)
4.8/5
(40)

Preceding activities are those that must occur before others can be done.

(True/False)
4.9/5
(40)

The overall effect of laddering activities is to:

(Multiple Choice)
4.8/5
(36)
Showing 41 - 60 of 98
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)