Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.9/5
(47)

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
4.9/5
(42)

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
5.0/5
(34)

The late start time should be calculated using a forward pass through the network.

(True/False)
4.8/5
(33)

Activity Z has estimates a=5, b=10, m=7; activity X has estimates a=4, b=11, m=6; and activity Y has estimates a=3, b=12, m=8. Which of the following statements is best?

(Multiple Choice)
4.8/5
(39)

What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?

(Essay)
4.9/5
(40)

Prior to creating a network, it is important to:

(Multiple Choice)
4.8/5
(34)

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.9/5
(41)

The variance of an activity is given by:

(Multiple Choice)
4.9/5
(31)

An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected duration of the activity?

(Multiple Choice)
4.8/5
(31)

Which of these statements about this network is best? Which of these statements about this network is best?

(Multiple Choice)
4.8/5
(32)

One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):

(Multiple Choice)
4.7/5
(43)

An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time. If the activity variance is 10, what is the expected time?

(Multiple Choice)
4.9/5
(40)

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?

(Multiple Choice)
4.8/5
(34)

The late finish times are determined by taking a(n) __________ through the network.

(Short Answer)
4.8/5
(41)

What is the early start time for Activity G given the activity times and precedence requirements shown in the table? What is the early start time for Activity G given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.8/5
(42)

Concurrent activities are:

(Multiple Choice)
4.9/5
(38)

Compute early and late start and finish times for the network shown. Compute early and late start and finish times for the network shown.

(Essay)
5.0/5
(45)

Because an activity's pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate, the __________ better represents the distribution of possible alternative durations.

(Short Answer)
4.9/5
(37)

The term ordered activity means:

(Multiple Choice)
4.8/5
(40)
Showing 21 - 40 of 98
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)