Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.9/5
(47)
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. 

(Multiple Choice)
4.9/5
(42)
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. 

(Multiple Choice)
5.0/5
(34)
The late start time should be calculated using a forward pass through the network.
(True/False)
4.8/5
(33)
Activity Z has estimates a=5, b=10, m=7; activity X has estimates a=4, b=11, m=6; and activity Y has estimates a=3, b=12, m=8. Which of the following statements is best?
(Multiple Choice)
4.8/5
(39)
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
(Essay)
4.9/5
(40)
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.9/5
(41)
An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected duration of the activity?
(Multiple Choice)
4.8/5
(31)
One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):
(Multiple Choice)
4.7/5
(43)
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time. If the activity variance is 10, what is the expected time?
(Multiple Choice)
4.9/5
(40)
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity? 

(Multiple Choice)
4.8/5
(34)
The late finish times are determined by taking a(n) __________ through the network.
(Short Answer)
4.8/5
(41)
What is the early start time for Activity G given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.8/5
(42)
Because an activity's pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate, the __________ better represents the distribution of possible alternative durations.
(Short Answer)
4.9/5
(37)
Showing 21 - 40 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)