Exam 11: Critical Chain Project Scheduling
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
The student syndrome of wasting extra safety time can be described as:
(Multiple Choice)
5.0/5
(45)
Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
(Multiple Choice)
4.9/5
(42)
Why aren't both negative and positive project variation passed along a project network path?
(Essay)
4.8/5
(33)
A project consists of three activities with information as shown in the table.What is the overall standard deviation of the project? 

(Multiple Choice)
4.8/5
(36)
CCPM advocates modification of the project schedule from an early-start to a(n)________ approach.
(Essay)
4.8/5
(36)
In applying the principle of common cause variation to the theory of CCPM,it is important to:
(Multiple Choice)
4.7/5
(39)
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Newbold's model to determine the aggregated buffer of one standard deviation for this project. 

(Multiple Choice)
4.9/5
(47)
A project consists of three activities with information as shown in the table.What is the overall variance of the project? 

(Multiple Choice)
4.9/5
(39)
The term capacity constraint buffer refers to a safety margin separating different tasks scheduled to use the same resource.
(True/False)
4.8/5
(36)
Your next project consists of 8 consecutive 8-day activities,each estimated by a different worker in your organization.Your organizational culture dictates that you add your own safety margin of 3 days into your estimates.Unbeknownst to you,the project manager has recently converted to a critical chain project management view.The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place.What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule?
(Multiple Choice)
4.8/5
(34)
Both positive and negative variations are usually passed downstream during a project.
(True/False)
4.9/5
(33)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(42)
People have a tendency to focus on responsibilities with long end-date completions and minimize the importance of more near-term deadlines.
(True/False)
4.8/5
(43)
Which statement about critical chain project management is best?
(Multiple Choice)
4.9/5
(39)
A project consists of three activities with information as shown in the table.What is the overall standard deviation of the project? 

(Multiple Choice)
4.8/5
(43)
List any three criticisms of critical chain project management and rank them in order from the greatest to smallest threat to universal adoption of CCPM.
(Essay)
4.8/5
(42)
What are the formal steps to apply CCPM to multiple project portfolios?
(Essay)
4.9/5
(45)
The best thing a project manager can do when noticing common cause variation in a project's monthly budget summary is to:
(Multiple Choice)
4.7/5
(36)
A complex project concludes with three paths merging into a final activity,after which the project is completed.Two of these paths are non-critical and have been managed effectively,with slack remaining.The critical path has also been managed well and is on time entering the merge node.Which statement is best?
(Multiple Choice)
4.9/5
(32)
Showing 61 - 80 of 117