Exam 11: Critical Chain Project Scheduling
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
Project managers often add a(n)________ to individual workers' estimates of activity duration.
(Essay)
4.8/5
(32)
When choosing the most viable solution to resource conflict issues,the best option is the one that:
(Multiple Choice)
4.8/5
(35)
Parkinson's Law states that work expands to fill the time available.
(True/False)
4.8/5
(47)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(34)
The Central Limit Theorem states that if a number of probability distributions are summed,the variance of the sum equals the sum of the variances of individual distributions.
(True/False)
4.7/5
(36)
Create a 5-activity example and use it to explain the difference between the critical path method and critical chain project management.
(Essay)
4.9/5
(37)
What is the difference between common cause and special cause variation? In what ways does the difference between the two manifest itself in project management?
(Essay)
4.8/5
(41)
Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.A feeder buffer should be placed immediately before: 

(Multiple Choice)
4.9/5
(34)
A worker is assigned three tasks,A,B,and C,each having a duration of 20 days.One approach to completing these tasks would be to focus on one at a time,complete it,and then move to the second,followed by the third.One multitasking approach would call for dividing each task in half and rotating from one to the other so that the first halves of A,B,and C are completed before the second halves of A,B,and C are completed (always in this order)and so on until the activities are finished.What is the difference in the average completion times for the multitasked activities?
(Multiple Choice)
4.9/5
(40)
In order to estimate completion of a Gaussian,or lognormal,distributed activity time with a 90% or higher degree of confidence,the time may be overestimated by as much as:
(Multiple Choice)
4.9/5
(39)
All five members of a project team add 15% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 10% for his personal safety margin.Then,anticipating a cut by top management,he adds another 10% to his final project estimate.Much to his surprise,top management cuts 30% off his time estimate.How much of a cushion is now built into the project?
(Multiple Choice)
4.8/5
(37)
All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 20% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.The executive level of the organization just completed a retreat where they read The One Minute Manager,Who Moved My Cheese,and Critical Chain.They return from their retreat both energized and much wiser in the ways of project management.They know that everyone has been routinely adding 20% and want to scale the project back to an unpadded estimate.How much should they cut?
(Multiple Choice)
4.9/5
(39)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology? 

(Multiple Choice)
4.9/5
(40)
A worker is assigned three tasks,A,B,and C,each having a duration of 20 days.One approach to completing these tasks would be to focus on one at a time,complete it,and then move to the second,followed by the third.One multitasking approach would call for dividing each task into fifths and rotating from one to the other so that the first fifths of A,B,and C are completed before the second fifths of A,B,and C are completed (always in this order)and so on until the activities are finished.What is the difference in the average completion times for the multitasked activities?
(Multiple Choice)
4.9/5
(46)
The buffers supplied to non-critical paths in critical chain project management are called:
(Multiple Choice)
5.0/5
(41)
The first step in the TOC (Theory of Constraints)methodology is to ________.
(Essay)
4.9/5
(36)
Showing 81 - 100 of 117
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)