Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.



(Multiple Choice)
4.9/5
(32)
Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.
(True/False)
4.8/5
(27)
Use the Gantt chart and the activity list to determine when resource 2 is free.



(Multiple Choice)
4.9/5
(28)
The primary drawback with ________ occurs when the project is very complex,with numerous paths through the model.
(Essay)
4.8/5
(37)
Networks are adaptable and useful for all scheduling challenges that an organization faces.
(True/False)
4.9/5
(36)
Use the Gantt chart and activity list to determine which resource has the greatest continual use.



(Multiple Choice)
4.8/5
(32)
What is the early start time for activity C if it has the start to start relationship shown? 

(Multiple Choice)
4.8/5
(33)
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.



(Multiple Choice)
4.8/5
(26)
The logical relationship between the start and finish of one activity and the start and finish of another activity is the ________.
(Essay)
4.7/5
(39)
Mick has a project consisting of eight activities as listed in the table (with durations in days).He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Determine the early and late start and finish times for all of these activities.



(Essay)
4.8/5
(36)
Determine early start and early finish times for all activities in this network.Activity duration in days appears under each arrow. 

(Essay)
4.9/5
(31)
The most common type of logical sequencing between tasks is referred to as the:
(Multiple Choice)
5.0/5
(26)
In order to accelerate completion of a project,the manager must crash critical path activities.
(True/False)
4.9/5
(39)
What is project crashing and what are three reasons why it might be important to do so?
(Essay)
4.7/5
(28)
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.



(Multiple Choice)
4.8/5
(33)
For large projects,network diagrams are more useful if they are completely detailed.
(True/False)
4.8/5
(33)
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? 

(Multiple Choice)
4.8/5
(38)
Which of these approaches will NOT accelerate the completion of a project?
(Multiple Choice)
4.8/5
(29)
An activity of duration zero whose sole purpose is to maintain network logic is a(n)________.
(Essay)
4.8/5
(37)