Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Which of the activities in the diagram have slack? Which of the activities in the diagram have slack?

(Multiple Choice)
4.8/5
(34)

Dummy activities are used in AOA networks to indicate the existence of precedent relationships between activities and their event nodes.

(True/False)
4.9/5
(41)

The AOA network described by this table needs: The AOA network described by this table needs:

(Multiple Choice)
4.7/5
(36)

The three principal methods for accelerating project activities are to change the ________,________,and ________ of the project resources.

(Essay)
4.9/5
(30)

An AOA network:

(Multiple Choice)
4.9/5
(38)

A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?

(Multiple Choice)
4.7/5
(41)

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days? A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days?

(Multiple Choice)
5.0/5
(32)

Use the Gantt chart and activity list to determine which resource is used the least. Use the Gantt chart and activity list to determine which resource is used the least.    Use the Gantt chart and activity list to determine which resource is used the least.

(Multiple Choice)
4.9/5
(33)

The AOA network described by this table needs: The AOA network described by this table needs:

(Multiple Choice)
4.9/5
(35)

AON networks have an advantage over AOA networks:

(Multiple Choice)
4.8/5
(34)

The process of accelerating a project is referred to as ________.

(Essay)
4.8/5
(27)

The two primary drawbacks to the use of overtime as a means of crashing a product are the ________ and the ________.

(Essay)
4.9/5
(35)

Sketch the network described in the table in AOA format. Sketch the network described in the table in AOA format.

(Essay)
4.9/5
(29)

Consider the project described by the table where all durations are in days and the costs in dollars.What is the minimum cost of completing this project in 150 days? Consider the project described by the table where all durations are in days and the costs in dollars.What is the minimum cost of completing this project in 150 days?

(Essay)
4.9/5
(27)

PERT analysis is based on ________ estimates,which,if unreasonably determined,can lead to inaccurate and misleading project schedules.

(Essay)
4.7/5
(34)

What are four criticisms and caveats to bear in mind as you develop a project activity network?

(Essay)
4.9/5
(39)

In an actual project,one means of crashing critical path activities would be to perform at a lower level of quality.

(True/False)
4.8/5
(41)

Start-to-start lags are becoming increasingly used as a means to accelerate projects through a process known as ________.

(Essay)
5.0/5
(32)

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days? A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days?

(Multiple Choice)
4.8/5
(31)

How might a project manager alter a straightforward PERT network to accommodate an inordinately large and complex project?

(Essay)
4.9/5
(39)
Showing 81 - 100 of 110
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)