Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.

(True/False)
4.9/5
(44)

Most project management software employs AOA diagramming

(True/False)
4.8/5
(33)

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days? A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days?

(Multiple Choice)
4.8/5
(36)

It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days. It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.

(Multiple Choice)
5.0/5
(35)

Use the Gantt chart and activity list to determine which resource has the greatest continual use. Use the Gantt chart and activity list to determine which resource has the greatest continual use.    Use the Gantt chart and activity list to determine which resource has the greatest continual use.

(Multiple Choice)
4.9/5
(29)

Use the Gantt chart and activity list to determine which resource is used the least. Use the Gantt chart and activity list to determine which resource is used the least.    Use the Gantt chart and activity list to determine which resource is used the least.

(Multiple Choice)
4.9/5
(32)

Use the Gantt chart and the activity list to determine when resource 5 is free. Use the Gantt chart and the activity list to determine when resource 5 is free.    Use the Gantt chart and the activity list to determine when resource 5 is free.

(Multiple Choice)
4.8/5
(34)

The heir to the throne was due 56 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.The seven activities,their normal and expedited times (in days)and costs appear in the table.What is the minimum cost to ensure that this project is completed in 56 days? Which activities should be reduced and by how many days? The heir to the throne was due 56 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.The seven activities,their normal and expedited times (in days)and costs appear in the table.What is the minimum cost to ensure that this project is completed in 56 days? Which activities should be reduced and by how many days?

(Essay)
4.9/5
(35)

AOA is a more useful technique than AON if the project is complex and has many significant milestones.

(True/False)
4.9/5
(38)

What are the strengths and weaknesses of AOA and AON techniques?

(Essay)
4.9/5
(36)
Showing 101 - 110 of 110
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)