Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible? 

(Multiple Choice)
4.8/5
(35)
What are the three principal methods for accelerating a project and under what circumstances might these methods yield little gain?
(Essay)
4.9/5
(26)
What is the minimum completion cost of this project if there is a penalty of $1,000 for each day the project lasts longer than 27 days? Activity durations in days and crash costs in dollars are given in the table.



(Essay)
4.8/5
(40)
What information is NOT included in the nodes for an AOA network?
(Multiple Choice)
4.8/5
(37)
Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? 

(Multiple Choice)
4.9/5
(32)
A(n)________ relationship is appropriate where two or more linked activities must be completed before a successor is begun.
(Essay)
4.7/5
(30)
If an activity's cost is plotted against its duration on axes with zeros at the origin:
(Multiple Choice)
4.8/5
(30)
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?
(Multiple Choice)
4.8/5
(40)
In analyzing crash options for project activities,each activity has a slope that is calculated as the ________ divided by the ________.
(Essay)
4.9/5
(39)
Sketch a network and use it as an example as you discuss the four different logical relationships between activities.
(Essay)
4.8/5
(37)
Use the Gantt chart and activity list to determine when resource 3 is free.



(Multiple Choice)
4.9/5
(34)
Use the Gantt chart and activity list to determine which resource is used the most.



(Multiple Choice)
4.8/5
(36)
Mick has a project consisting of eight activities (listed in the table with durations and precedence requirements)to complete.He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below.Discuss any issues with the apprentice's diagram.



(Essay)