Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
The most common type of logical sequencing between tasks is the ________ relationship.
(Essay)
4.8/5
(38)
Use the Gantt chart and the activity list to determine which resource is used the least.



(Multiple Choice)
4.9/5
(28)
If a project is extraordinarily complex,rather than showing every possible path through the network and every activity sequence,a(n)________ that shows only the key subroutines or network paths can be created.
(Essay)
4.8/5
(27)
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks? 

(Multiple Choice)
5.0/5
(34)
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? 

(Multiple Choice)
4.8/5
(35)
Given the cost information in the table,what is the cheapest activity to crash on a per week basis? 

(Multiple Choice)
4.8/5
(34)
The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.The seven activities,their normal and expedited times (in days)and costs appear in the table.Just to be on the safe side,he decided to bring the project in at 53 days in case the delivery was a week early.Tell him what the least expensive 53-day project is;which activities should be reduced in duration,by how many days,and at the total cost,so he can roll up the sleeves on his "World's Greatest Dad" sweatshirt,and get to work.


(Essay)
4.9/5
(33)
________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
(Essay)
4.9/5
(39)
Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project. 

(Multiple Choice)
4.8/5
(41)
Use the Gantt chart and activity list to determine which resource is used the most.



(Multiple Choice)
4.7/5
(31)
Use the information in the table (all times are in days)to determine the lowest cost minimum completion time? 

(Multiple Choice)
4.8/5
(37)
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? 

(Multiple Choice)
4.8/5
(32)
A complex project that is managed using a top-down,bottom-up approach to network diagrams means that:
(Multiple Choice)