Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The most common type of logical sequencing between tasks is the ________ relationship.

(Essay)
4.8/5
(38)

Each individual bar on a Gantt chart represents a(n)________.

(Essay)
4.9/5
(32)

Use the Gantt chart and the activity list to determine which resource is used the least. Use the Gantt chart and the activity list to determine which resource is used the least.    Use the Gantt chart and the activity list to determine which resource is used the least.

(Multiple Choice)
4.9/5
(28)

Research has shown that,in general:

(Multiple Choice)
4.8/5
(35)

Gantt charts can display early start or late start logic.

(True/False)
4.9/5
(34)

If a project is extraordinarily complex,rather than showing every possible path through the network and every activity sequence,a(n)________ that shows only the key subroutines or network paths can be created.

(Essay)
4.8/5
(27)

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks? A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks?

(Multiple Choice)
5.0/5
(34)

One reason for crashing a project is:

(Multiple Choice)
4.8/5
(31)

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?

(Multiple Choice)
4.8/5
(35)

Given the cost information in the table,what is the cheapest activity to crash on a per week basis? Given the cost information in the table,what is the cheapest activity to crash on a per week basis?

(Multiple Choice)
4.8/5
(34)

The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.The seven activities,their normal and expedited times (in days)and costs appear in the table.Just to be on the safe side,he decided to bring the project in at 53 days in case the delivery was a week early.Tell him what the least expensive 53-day project is;which activities should be reduced in duration,by how many days,and at the total cost,so he can roll up the sleeves on his "World's Greatest Dad" sweatshirt,and get to work. The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.The seven activities,their normal and expedited times (in days)and costs appear in the table.Just to be on the safe side,he decided to bring the project in at 53 days in case the delivery was a week early.Tell him what the least expensive 53-day project is;which activities should be reduced in duration,by how many days,and at the total cost,so he can roll up the sleeves on his World's Greatest Dad sweatshirt,and get to work.

(Essay)
4.9/5
(33)

Finish to start lags are the same as additional activity slack.

(True/False)
4.8/5
(34)

________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.

(Essay)
4.9/5
(39)

Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project. Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project.

(Multiple Choice)
4.8/5
(41)

Use the Gantt chart and activity list to determine which resource is used the most. Use the Gantt chart and activity list to determine which resource is used the most.    Use the Gantt chart and activity list to determine which resource is used the most.

(Multiple Choice)
4.7/5
(31)

Use the information in the table (all times are in days)to determine the lowest cost minimum completion time? Use the information in the table (all times are in days)to determine the lowest cost minimum completion time?

(Multiple Choice)
4.8/5
(37)

The critical path of this network is: The critical path of this network is:

(Multiple Choice)
4.9/5
(38)

The fastest completion time for this project is: The fastest completion time for this project is:

(Multiple Choice)
4.8/5
(31)

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?

(Multiple Choice)
4.8/5
(32)

A complex project that is managed using a top-down,bottom-up approach to network diagrams means that:

(Multiple Choice)
4.9/5
(28)
Showing 61 - 80 of 110