Exam 6: Managing Project Scheduling
Exam 1: Lntroduction to Project Management105 Questions
Exam 2: The Project Management Life Cycle119 Questions
Exam 3: Managing Project Teams139 Questions
Exam 4: Managing Project Communication101 Questions
Exam 5: Managing Project Scope118 Questions
Exam 6: Managing Project Scheduling114 Questions
Exam 7: Managing Project Resources120 Questions
Exam 8: Managing Project Quality127 Questions
Exam 9: Managing Project Risk111 Questions
Exam 10: Managing Project Procurement121 Questions
Exam 11: Managing Project Execution53 Questions
Exam 12: Managing Project Control and Closure110 Questions
Exam 13: Understanding Task Dependencies, Resource Allocation, and Progress Tracking57 Questions
Select questions type
A project can be broken down by the major deliverables, phases of the project life cycle,____________, or a combination of these.
(Short Answer)
4.7/5
(37)
A WBS is the output that results from the process of dividing a____________ into more manageable tasks.
(Short Answer)
4.9/5
(31)
A____________ dependency indicates that a second activity cannot be started until the first activity has been completed.
(Short Answer)
4.8/5
(32)
A____________ provides additional detail about the individual components of a WBS.
(Short Answer)
4.8/5
(29)
Network____________ are templates developed from previous projects used to shorten the development time of network diagrams.
(Multiple Choice)
4.8/5
(30)
____________are important dates within a project schedule that are meaningful in terms of the completion of specific sets of project events.
(Short Answer)
4.9/5
(41)
List the three forms of dependencies between project activities and provide examples for each.
(Essay)
4.8/5
(39)
During the planning stage, a project management team might not be able to decompose some of the project's later components.
(True/False)
5.0/5
(40)
____________dependencies indicate the relationship of project activities and external events.
(Short Answer)
4.8/5
(44)
Activity definition is the process of ____________and defining activities that must be performed to produce project deliverables.
(Short Answer)
4.8/5
(36)
____________is the time delay between completion of one task and the start of the successor.
(Short Answer)
4.9/5
(44)
Cone of uncertainty is a scheduling technique that requires greater cost and schedule refinement regarding upcoming activities in the project schedule.
(True/False)
4.7/5
(39)
Showing 81 - 100 of 114
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)