Schedules are rarely perfect.

(True/False)
5.0/5
(43)

The project scope statement, the WBS, and the WBS dictionary form the project management plan.

(True/False)
4.9/5
(35)

An activity has a____________ deliverable.

(Short Answer)
4.8/5
(40)

A chart that employs timelines and other types of symbols to illustrate the project schedule is called____________ .

(Short Answer)
4.8/5
(34)

The output that results from the process of dividing the entire project into manageable tasks is called:

(Multiple Choice)
4.9/5
(41)

All of the following are estimation phases EXCEPT:

(Multiple Choice)
4.8/5
(37)

Project schedules may be created for different purposes and may have different levels of detail.

(True/False)
4.7/5
(29)

When determining the sequence of activities, the project manager should take some constraints into account. These can fall into the following category/categories:

(Multiple Choice)
4.8/5
(30)

A product breakdown structure is also referred to as bill of materials.

(True/False)
4.7/5
(38)

ADM is better than PDM for illustrating different task dependencies.

(True/False)
4.8/5
(38)

Schedules are:

(Multiple Choice)
4.9/5
(33)

The scope baseline includes:

(Multiple Choice)
4.8/5
(28)

The estimation phases of project progress, in decreasing order, are:

(Multiple Choice)
4.8/5
(36)

Budgetary estimates have the greatest variation.

(True/False)
4.9/5
(33)

Lists of activities from prior projects are called:

(Multiple Choice)
4.9/5
(36)

A ____________dependency indicates that the start of a successor depends on the start of the predecessor.

(Short Answer)
4.8/5
(34)

Project scheduling is the process of defining activities,____________ , and estimating their duration.

(Short Answer)
4.8/5
(36)

A PBS is the output that results from the process of dividing a____________ into the individual components.

(Short Answer)
4.9/5
(42)

____________is a scheduling technique that requires greater cost and schedule refinement regarding upcoming activities in the project schedule.

(Multiple Choice)
4.9/5
(38)

____________is the time delay between completion of one task and the start of the successor.

(Multiple Choice)
4.8/5
(33)