Exam 6: Managing Project Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A finish- to- start dependency indicates that the completion of the successor depends on the beginning of the predecessor.

(True/False)
4.8/5
(35)

A network diagram is a schematic display that illustrates the various tasks in a project as well as their____________ .

(Short Answer)
4.7/5
(43)

Too much detail of the work packages can lead to____________ .

(Short Answer)
4.9/5
(38)

A WBS dictionary:

(Multiple Choice)
5.0/5
(44)

The need to delay activities requiring more funding to later stages of a project is an example of the following constraint(s):

(Multiple Choice)
4.8/5
(41)

An activity has well- defined ____________ steps.

(Short Answer)
4.7/5
(44)

Budgetary estimates can vary by as much as:

(Multiple Choice)
4.9/5
(34)

____________estimates vary from +25% to - 10%.

(Short Answer)
4.8/5
(41)

Subcomponents of control accounts are referred to as planning packages.

(True/False)
4.8/5
(32)

A work package should be relatively____________.

(Short Answer)
4.8/5
(38)

Higher level components that are broken down at later stages are called:

(Multiple Choice)
4.7/5
(29)

A diagramming method using arrows to represent activities and their precedence relationships, and nodes to represent project milestones is called:

(Multiple Choice)
4.8/5
(37)

A ____________ is an activity of zero duration that is used to show a logical relationship or dependency in a network diagram.

(Short Answer)
4.8/5
(41)

A project can be broken down in a variety of ways.

(True/False)
4.8/5
(37)

____________dependencies indicate the relationship of activities that cannot be performed in parallel.

(Multiple Choice)
4.9/5
(34)

Each component in the WBS has to be the____________ of all lower- level deliverables on the same branch.

(Short Answer)
4.8/5
(31)

____________dependencies indicate the relationship of project activities and external events.

(Multiple Choice)
4.7/5
(38)

What is NOT among the top- five project management challenges?

(Multiple Choice)
4.8/5
(35)

An activity is____________ .

(Short Answer)
4.8/5
(31)

Another term for a product breakdown structure is:

(Multiple Choice)
4.9/5
(30)
Showing 61 - 80 of 114