To find the standard deviation of the critical path, you must first add the ________ of all activities on the critical path.

Free
(Short Answer)
4.8/5
(38)
Correct Answer:
Verified

variances

Figure to accompany Table 7.1 Figure to accompany Table 7.1     Table 7.1    -Using the information shown in Table 7.1, what is the slack time for activity D? Table 7.1 Figure to accompany Table 7.1     Table 7.1    -Using the information shown in Table 7.1, what is the slack time for activity D? -Using the information shown in Table 7.1, what is the slack time for activity D?

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
Verified

A

Figure to accompany Table 7.1 Figure to accompany Table 7.1     Table 7.1    -Using the information shown in Table 7.1, what is the earliest finish time for activity A? Table 7.1 Figure to accompany Table 7.1     Table 7.1    -Using the information shown in Table 7.1, what is the earliest finish time for activity A? -Using the information shown in Table 7.1, what is the earliest finish time for activity A?

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

B

Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks). Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks).    -Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase? -Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.8/5
(31)

The ________ is determined by starting with the normal time schedule and crashing activities along the critical path in such a way that the costs of crashing do not exceed the savings in indirect and penalty costs.

(Short Answer)
4.8/5
(39)

Table 7.6 Table 7.6    -Using Table 7.6, what is the critical path for this project? -Using Table 7.6, what is the critical path for this project?

(Multiple Choice)
4.9/5
(29)

Project managers should be able to organize a set of disparate activities.

(True/False)
4.8/5
(31)

Table 7.5 Table 7.5    -Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated? -Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated?

(Multiple Choice)
4.8/5
(31)

Figure to accompany Table 7.7 Figure to accompany Table 7.7     Table 7.7    -If a decision is made to crash activity D in Table 7.7 by one week, what is the cost for this one week of crashing? Table 7.7 Figure to accompany Table 7.7     Table 7.7    -If a decision is made to crash activity D in Table 7.7 by one week, what is the cost for this one week of crashing? -If a decision is made to crash activity D in Table 7.7 by one week, what is the cost for this one week of crashing?

(Multiple Choice)
4.8/5
(39)

Table 7.8 Table 7.8    -Using Table 7.8, what is the minimum crashing cost to finish this project in 18 days? -Using Table 7.8, what is the minimum crashing cost to finish this project in 18 days?

(Multiple Choice)
4.9/5
(33)

Table 7.4 Table 7.4    -Using Table 7.4, what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date? -Using Table 7.4, what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?

(Multiple Choice)
4.9/5
(45)

Following the project defining and organizing phase, project planning involves five steps. List and briefly describe these five planning steps as applied to writing a term paper for an Operations Management class.

(Essay)
4.8/5
(32)

What options do project managers have to alleviate resource problems? Briefly describe each method.

(Essay)
4.8/5
(38)

Figure to accompany Table 7.7 Figure to accompany Table 7.7     Table 7.7    -How many weeks of crashing are available for activity C in Table 7.7? Table 7.7 Figure to accompany Table 7.7     Table 7.7    -How many weeks of crashing are available for activity C in Table 7.7? -How many weeks of crashing are available for activity C in Table 7.7?

(Multiple Choice)
4.8/5
(35)

Figure to accompany Table 7.7 Figure to accompany Table 7.7     Table 7.7    -Which activity should be crashed first for the project shown in Table 7.7? Table 7.7 Figure to accompany Table 7.7     Table 7.7    -Which activity should be crashed first for the project shown in Table 7.7? -Which activity should be crashed first for the project shown in Table 7.7?

(Multiple Choice)
4.8/5
(38)

Table 7.5 Table 7.5    -Using Table 7.5, what is the earliest that activity D can be finished? -Using Table 7.5, what is the earliest that activity D can be finished?

(Multiple Choice)
4.9/5
(32)

The phase of project management that takes the most resources is the execution phase.

(True/False)
4.9/5
(34)

Table 7.13 All activity times for the project are in weeks. Table 7.13 All activity times for the project are in weeks.    -Using Table 7.13, if the expected time for activity H is changed to 25 weeks, by how many weeks will the project's expected completion time increase? -Using Table 7.13, if the expected time for activity H is changed to 25 weeks, by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.9/5
(39)

Which one of the following best describes the critical path of a PERT/CPM network?

(Multiple Choice)
4.8/5
(28)

Table 7.8 Table 7.8    -Using Table 7.8, what is the latest start time for activity E? -Using Table 7.8, what is the latest start time for activity E?

(Multiple Choice)
4.9/5
(42)