Exam 7: Project Management
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
To find the standard deviation of the critical path, you must first add the ________ of all activities on the critical path.
Free
(Short Answer)
4.8/5
(38)
Correct Answer:
variances
Figure to accompany Table 7.1
Table 7.1
-Using the information shown in Table 7.1, what is the slack time for activity D?


Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
A
Figure to accompany Table 7.1
Table 7.1
-Using the information shown in Table 7.1, what is the earliest finish time for activity A?


Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
B
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
-Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.8/5
(31)
The ________ is determined by starting with the normal time schedule and crashing activities along the critical path in such a way that the costs of crashing do not exceed the savings in indirect and penalty costs.
(Short Answer)
4.8/5
(39)
Table 7.6
-Using Table 7.6, what is the critical path for this project?

(Multiple Choice)
4.9/5
(29)
Project managers should be able to organize a set of disparate activities.
(True/False)
4.8/5
(31)
Table 7.5
-Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated?

(Multiple Choice)
4.8/5
(31)
Figure to accompany Table 7.7
Table 7.7
-If a decision is made to crash activity D in Table 7.7 by one week, what is the cost for this one week of crashing?


(Multiple Choice)
4.8/5
(39)
Table 7.8
-Using Table 7.8, what is the minimum crashing cost to finish this project in 18 days?

(Multiple Choice)
4.9/5
(33)
Table 7.4
-Using Table 7.4, what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?

(Multiple Choice)
4.9/5
(45)
Following the project defining and organizing phase, project planning involves five steps. List and briefly describe these five planning steps as applied to writing a term paper for an Operations Management class.
(Essay)
4.8/5
(32)
What options do project managers have to alleviate resource problems? Briefly describe each method.
(Essay)
4.8/5
(38)
Figure to accompany Table 7.7
Table 7.7
-How many weeks of crashing are available for activity C in Table 7.7?


(Multiple Choice)
4.8/5
(35)
Figure to accompany Table 7.7
Table 7.7
-Which activity should be crashed first for the project shown in Table 7.7?


(Multiple Choice)
4.8/5
(38)
Table 7.5
-Using Table 7.5, what is the earliest that activity D can be finished?

(Multiple Choice)
4.9/5
(32)
The phase of project management that takes the most resources is the execution phase.
(True/False)
4.9/5
(34)
Table 7.13
All activity times for the project are in weeks.
-Using Table 7.13, if the expected time for activity H is changed to 25 weeks, by how many weeks will the project's expected completion time increase?

(Multiple Choice)
4.9/5
(39)
Which one of the following best describes the critical path of a PERT/CPM network?
(Multiple Choice)
4.8/5
(28)
Table 7.8
-Using Table 7.8, what is the latest start time for activity E?

(Multiple Choice)
4.9/5
(42)