Exam 11: Resource Planning
Exam 1: Using Operations to Create Value115 Questions
Exam 2: Process Strategy and Analysis239 Questions
Exam 3: Quality and Performance198 Questions
Exam 4: Capacity Planning120 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems166 Questions
Exam 7: Project Management139 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management205 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning124 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration120 Questions
Exam 15: Supply Chain Sustainability78 Questions
Exam 16: Supplement A Decision Making107 Questions
Exam 17: Supplement J Operations Scheduling123 Questions
Exam 18: Supplement K Layout39 Questions
Exam 19: Supplement B Waiting Lines111 Questions
Exam 20: Supplement C Special Inventory Models53 Questions
Exam 21: Supplement D Linear Programming87 Questions
Exam 22: Supplement E Simulation54 Questions
Exam 23: Supplement F Financial Analysis55 Questions
Exam 24: Supplement G Acceptance Sampling Plans87 Questions
Exam 25: Supplement H Measuring Output Rates108 Questions
Exam 26: Supplement I Learning Curve Analysis50 Questions
Select questions type
Which one of the following is a feature of MRP II, but not available in basic MRP systems?
Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
A
The L4L rule is a special case of the ________.
Free
(Short Answer)
4.8/5
(37)
Correct Answer:
POQ rule
Dependent demand for an item occurs because the quantity required for it varies with the production plans of one or more parents.
Free
(True/False)
4.9/5
(41)
Correct Answer:
True
Explain why, in a dependent demand environment, MRP does a better job of estimating the need to replenish inventory items than does the reorder point system.
(Essay)
4.8/5
(41)
Use the bill of materials and inventory records to determine the additional quantities of purchased items necessary to assemble 20 end items if the manufacturer uses lot-for-lot ordering. There are no end items currently on hand, and none of the components have any scheduled receipts.
Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials.


(Essay)
4.8/5
(33)
The sums of the quantities in the master production schedule must equal those in the ________.
(Short Answer)
4.9/5
(32)
An ERP system revolves around a single comprehensive database that is made available across the entire organization.
(True/False)
4.7/5
(29)
Scenario 11.3
Use this bill of materials and inventory records to answer the questions.
-Use Scenario 11.3 to answer this question. How many additional units of N are required to produce 25 end items?


(Multiple Choice)
4.8/5
(34)
Under which one of the following circumstances can an MRP system be used to its best advantage?
(Multiple Choice)
4.8/5
(33)
The companies SAP AG and Microsoft have the largest installed base of customers for ERP packages.
(True/False)
4.9/5
(26)
Which of the following is not used to derive an item's gross requirements?
(Multiple Choice)
5.0/5
(32)
Which one of the following statements about lot-sizing rules is True?
(Multiple Choice)
4.9/5
(34)
One thing that an MRP II system has that an MRP system does not is ________.
(Essay)
4.8/5
(32)
Scenario 11.2
Inventory amounts indicated in the table are available to produce the end item indicated in this bill of materials.
-Use Scenario 11.2 to answer this question. How many additional units of F are needed to produce twelve end items?


(Multiple Choice)
4.8/5
(26)
The portion of the master production schedule farthest into the future is often frozen to reduce forecasting requirements.
(True/False)
4.9/5
(42)
Planned receipts are estimates of the amount of inventory available each week after gross requirements have been satisfied.
(True/False)
4.9/5
(34)
Consider the MPS, BOM, and inventory data shown.
Master Production Schedule:
The following table shows the MPS start quantities for the next 10 weeks.
Bill of Material:
- Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B.
- Subassembly B uses 2 each of component E.
Selected Inventory Data:
Construct the MRP schedule using the preceding information.


(Essay)
4.8/5
(38)