Exam 21: Learning Curves

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which one of the following statements about learning curves is TRUE?

(Multiple Choice)
4.8/5
(30)

The learning curve in the steel industry and the learning curve in disk memory drives have both been estimated at 79 percent.

(True/False)
4.9/5
(34)

The formula approach to learning curve calculations allows us to determine the hours required for any unit.

(True/False)
4.8/5
(44)

It took 60 hours to make the first unit of a product. After the second and third units were made, the learning curve was estimated to be 80%. At $10 per hour, estimate the labor bill for the fourth unit. (Use at least three decimals in the exponent if you use the formula approach.)

(Multiple Choice)
4.8/5
(43)

It took 18 hours to complete the first two products with an 80% learning curve. How long did the second product take?

(Multiple Choice)
4.9/5
(34)

The first unit of a product took 50 hours to build, and the learning curve is 85%. How long will it take to make the 20th unit? (Use at least three decimals in the exponent if you use the formula approach.)

(Multiple Choice)
4.9/5
(36)

The fourth unit of production took 80 minutes while the ninth unit of production took 50 minutes. How long did the first unit take?

(Short Answer)
4.9/5
(23)

Your company is making experimental turbochargers for a new design of high-powered farm tractors. The production schedule for these new components is contained in the table below. Your company is making experimental turbochargers for a new design of high-powered farm tractors. The production schedule for these new components is contained in the table below.    The first turbocharger, a trial unit (not part of the 3 required in Month 1), took 1100 hours to produce. Based on your experience with similar products, the learning curve is 80%. You have 22 employees, and each employee works 160 hours per month. How many hours will be required in each month? In which month(s) will overtime be required to meet the production schedule? The first turbocharger, a trial unit (not part of the 3 required in Month 1), took 1100 hours to produce. Based on your experience with similar products, the learning curve is 80%. You have 22 employees, and each employee works 160 hours per month. How many hours will be required in each month? In which month(s) will overtime be required to meet the production schedule?

(Essay)
4.9/5
(36)

What is the basic premise underlying the learning curve?

(Essay)
4.8/5
(30)

Your firm has a contract to make 20 specialty lenses for night vision equipment. The first one took 40 hours. Learning is expected at the 85% learning curve. How long will it take to finish all 20 units?

(Essay)
4.8/5
(31)

A job requires 20 hours for the initial unit and 12.8 hours for the fourth unit. What is the learning rate?

(Multiple Choice)
4.9/5
(38)

The first unit took 79 hours; the tenth took 46 hours. What learning curve is implied by the data?

(Essay)
4.8/5
(35)

In the formula approach to learning curve calculations, you have used the formula TN = T1 (Nb). For a problem with a 92 percent learning curve, what is b?

(Essay)
4.9/5
(34)

The fourth unit of production took 9 hours. If the learning curve is 90%, how long did the first unit take?

(Multiple Choice)
4.8/5
(33)

A defense contractor has just started producing engines for a new government contract. The first engine took 800 hours to produce. If the learning curve is 80%, approximately how long will it take to produce the first 20 engines?

(Multiple Choice)
4.7/5
(34)

Your firm has expertise with a special type of hand-finished furniture. The learning curve is known to be 82%. If the first piece of furniture took 6 hours, estimate (using the doubling approach) how long it will take to complete the third unit.

(Essay)
4.9/5
(38)

The Learning-Curve Coefficients table reports that for 90 percent learning, the sixteenth unit has a unit time value of 0.656. Verify that table entry by use of the doubling method.

(Essay)
4.9/5
(38)

To use the table of learning-curve coefficients, you must specify ________ and ________.

(Essay)
4.8/5
(20)

A project manager bases his time and labor estimates on a learning curve of 86%. The actual learning curve turns out to be 84%. The manager, because of the decreased learning, will complete his project in more time and with more labor use than his estimate suggested.

(True/False)
4.8/5
(38)

The first unit took 10 hours and the eighth unit took 5.12 hours. What is the learning curve?

(Multiple Choice)
4.8/5
(36)
Showing 81 - 100 of 114
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)