Exam 3: Project Management
Exam 1: Operations and Productivity138 Questions
Exam 2: Operations Strategy in a Global Environment134 Questions
Exam 3: Project Management131 Questions
Exam 4: Forecasting148 Questions
Exam 5: Design of Goods and Services126 Questions
Exam 6: Managing Quality226 Questions
Exam 7: Process Strategies259 Questions
Exam 8: Location Strategies233 Questions
Exam 9: Human Resources, Job Design, and Work Measurement321 Questions
Exam 10: Supply Chain Management158 Questions
Exam 11: Inventory Management230 Questions
Exam 12: Aggregate Planning and Sop122 Questions
Exam 13: Material Requirements Planning Mrp and Erp133 Questions
Exam 14: Short-Term Scheduling124 Questions
Exam 15: Lean Operations122 Questions
Exam 16: Maintenance and Reliability119 Questions
Exam 17: Decision-Making Tools101 Questions
Exam 18: Linear Programming102 Questions
Exam 19: Transportation Models92 Questions
Exam 20: Waiting-Line Models126 Questions
Exam 21: Learning Curves114 Questions
Exam 22: Simulation78 Questions
Exam 23: Applying Analytics to Big Data in Operations Management61 Questions
Select questions type
A project manager determined that the project was running behind schedule. If she wants to shorten the total completion, which of the following techniques should be used?
Free
(Multiple Choice)
4.7/5
(30)
Correct Answer:
A
Which of the following statements regarding critical paths is TRUE?
Free
(Multiple Choice)
4.9/5
(29)
Correct Answer:
D
In project management, crashing an activity must consider the impact on all paths in the network.
Free
(True/False)
4.9/5
(42)
Correct Answer:
True
Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.
(a) Given the project table below calculate the crash cost for 8 hours of time-savings.
(b) Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash. Pirmin has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?


(Essay)
4.8/5
(31)
Which of the following statements regarding PERT times is true?
(Multiple Choice)
4.8/5
(35)
Which of the following statements regarding PERT analysis is NOT true?
(Multiple Choice)
4.9/5
(32)
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?
(Multiple Choice)
4.9/5
(41)
Given the project within the table below, calculate the following:
(a) The critical path
(b) The minimum project duration
(c) The amount of slack for each activity


(Essay)
4.9/5
(32)
Ethical issues that may arise in projects large and small include:
(Multiple Choice)
4.8/5
(37)
Project management at the Tour de France races can be complex because:
(Multiple Choice)
4.8/5
(31)
Gantt charts give a timeline for each of a project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.
(True/False)
4.8/5
(36)
The ________ is a project management technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.
(Short Answer)
4.9/5
(35)
The network analysis method that allows activity times to vary is ________.
(Essay)
4.9/5
(31)
In a PERT network, non-critical activities that have little slack need to be monitored closely:
(Multiple Choice)
4.7/5
(43)
A network consists of the following list. Times are given in weeks.
(a) Draw the network diagram.
(b) Which activities form the critical path?
(c) How much slack exists at activities A and F?
(d) What is the duration of the critical path?

(Essay)
4.9/5
(40)
Consider the network presented in the following table. Calculate
(a) All possible paths
(b) The critical path
(c) The slack available at any non-critical points
(d) The minimum project duration


(Essay)
5.0/5
(41)