Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A project manager determined that the project was running behind schedule. If she wants to shorten the total completion, which of the following techniques should be used?

Free
(Multiple Choice)
4.7/5
(30)
Correct Answer:
Verified

A

Which of the following statements regarding critical paths is TRUE?

Free
(Multiple Choice)
4.9/5
(29)
Correct Answer:
Verified

D

In project management, crashing an activity must consider the impact on all paths in the network.

Free
(True/False)
4.9/5
(42)
Correct Answer:
Verified

True

Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. (a) Given the project table below calculate the crash cost for 8 hours of time-savings. (b) Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash. Pirmin has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. (a) Given the project table below calculate the crash cost for 8 hours of time-savings. (b) Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash. Pirmin has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?

(Essay)
4.8/5
(31)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.8/5
(35)

Which of the following statements regarding PERT analysis is NOT true?

(Multiple Choice)
4.9/5
(32)

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?

(Multiple Choice)
4.9/5
(41)

Given the project within the table below, calculate the following: (a) The critical path (b) The minimum project duration (c) The amount of slack for each activity Given the project within the table below, calculate the following: (a) The critical path (b) The minimum project duration (c) The amount of slack for each activity

(Essay)
4.9/5
(32)

Ethical issues that may arise in projects large and small include:

(Multiple Choice)
4.8/5
(37)

Describe agile projects.

(Short Answer)
4.9/5
(37)

Project management at the Tour de France races can be complex because:

(Multiple Choice)
4.8/5
(31)

Gantt charts give a timeline for each of a project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.

(True/False)
4.8/5
(36)

Projects such as road building and plane building are:

(Multiple Choice)
4.8/5
(29)

Which of the following is NOT a limitation of PERT?

(Multiple Choice)
4.8/5
(31)

The ________ is a project management technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.

(Short Answer)
4.9/5
(35)

The network analysis method that allows activity times to vary is ________.

(Essay)
4.9/5
(31)

In a PERT network, non-critical activities that have little slack need to be monitored closely:

(Multiple Choice)
4.7/5
(43)

What are some of the ethical issues faced by project managers?

(Essay)
4.8/5
(27)

A network consists of the following list. Times are given in weeks. A network consists of the following list. Times are given in weeks.    (a) Draw the network diagram. (b) Which activities form the critical path? (c) How much slack exists at activities A and F? (d) What is the duration of the critical path? (a) Draw the network diagram. (b) Which activities form the critical path? (c) How much slack exists at activities A and F? (d) What is the duration of the critical path?

(Essay)
4.9/5
(40)

Consider the network presented in the following table. Calculate (a) All possible paths (b) The critical path (c) The slack available at any non-critical points (d) The minimum project duration Consider the network presented in the following table. Calculate (a) All possible paths (b) The critical path (c) The slack available at any non-critical points (d) The minimum project duration

(Essay)
5.0/5
(41)
Showing 1 - 20 of 131
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)