Exam 17: Scheduling
Exam 1: Introduction to Operations and Supply Chain Management102 Questions
Exam 2: Quality Management88 Questions
Exam 3: Statistical Process Control157 Questions
Exam 4: Product Design95 Questions
Exam 5: Service Design91 Questions
Exam 6: Processes and Technology81 Questions
Exam 7: Capacity and Facilities Design128 Questions
Exam 8: Human Resources131 Questions
Exam 9: Project Management106 Questions
Exam 10: Supply Chain Management Strategy and Design72 Questions
Exam 11: Global Supply Chain Procurement and Distribution122 Questions
Exam 12: Forecasting92 Questions
Exam 13: Inventory Management127 Questions
Exam 14: Sales and Operations Planning123 Questions
Exam 15: Resource Planning97 Questions
Exam 16: Lean Systems88 Questions
Exam 17: Scheduling96 Questions
Select questions type
Managers typically use multiple objectives when constructing a schedule.
Free
(True/False)
4.8/5
(32)
Correct Answer:
True
Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below.
If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 4 is assigned to

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
C
If the following jobs are sequenced according to the DDATE rule, then the total number of jobs that would be late is (assume zero for today's date) 

Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
C
Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below:
If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 1 is assigned to

(Multiple Choice)
4.8/5
(28)
Tardiness is defined as the difference between a job's flow time and makespan.
(True/False)
4.9/5
(35)
The following set of jobs must be processed serially through a two-step system. If Johnson's Rule is used to sequence the jobs, then the order in which the jobs would be performed is 

(Multiple Choice)
5.0/5
(39)
Gantt charts show the planned and yet to be completed activities against total activities.
(True/False)
4.8/5
(32)
If the following jobs are sequenced according to the SLACK rule, then the mean tardiness (in days) for all jobs is (assume zero for today's date) 

(Multiple Choice)
4.7/5
(33)
The first-come, first-served (FCFS) sequencing rule should be only used when operating at high levels of capacity.
(True/False)
4.9/5
(42)
Input/output control provides the information necessary to regulate work flow in a job shop environment.
(True/False)
4.9/5
(26)
The difference between a job's due date and its completion time is known as
(Multiple Choice)
4.8/5
(36)
Which of the following is not typically considered an objective of scheduling?
(Multiple Choice)
4.9/5
(36)
If the work remaining is greater than the time remaining, the critical ratio (CR) will be
(Multiple Choice)
4.9/5
(40)
The process of assigning work to limited resources is known as scheduling.
(True/False)
5.0/5
(35)
Which of the following is considered one of the most flexible resources?
(Multiple Choice)
4.9/5
(34)
If the following jobs are sequenced according to the SLACK rule, then job A would be completed on day (assume zero for today's date) 

(Multiple Choice)
4.9/5
(33)
Sequencing involves determining the order in which jobs are released to the shop floor.
(True/False)
4.8/5
(38)
Determining the optimal allocation of jobs to machines or workers can be solved using the assignment method of linear programming.
(True/False)
4.7/5
(28)
Scheduling is considered the last stage of the planning process.
(True/False)
4.7/5
(33)
Showing 1 - 20 of 96
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)