Exam 17: Scheduling

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The sequence in which jobs should be processed is determined by using the linear programming.

(True/False)
4.8/5
(39)

Which of the following best describes a scheduling technique that sequences jobs as part of the loading decision and where resources are never loaded beyond capacity?

(Multiple Choice)
4.7/5
(47)

If the following jobs are sequenced according to the FCFS rule, then job C is completed on day (assume zero for today's date) If the following jobs are sequenced according to the FCFS rule, then job C is completed on day (assume zero for today's date)

(Multiple Choice)
4.9/5
(36)

If the following jobs are sequenced according to the SLACK rule, then the mean completion time (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the SLACK rule, then the mean completion time (in days) for all jobs is (assume zero for today's date)

(Multiple Choice)
4.8/5
(36)

If the following jobs are sequenced according to the LPT rule, then the mean tardiness (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the LPT rule, then the mean tardiness (in days) for all jobs is (assume zero for today's date)

(Multiple Choice)
4.8/5
(38)

Minimizing overtime is one of several objectives that could be considered when constructing a schedule.

(True/False)
4.8/5
(38)

The scheduling function for mass production and job shop production are basically the same.

(True/False)
4.7/5
(44)

A finite scheduling approach that concentrates on scheduling the bottleneck resource is known as

(Multiple Choice)
4.9/5
(47)

Describe scheduling techniques and list the objectives of scheduling.

(Essay)
4.9/5
(46)

If the following jobs are sequenced according to the SPT rule, then job B is completed on day (assume zero for today's date) If the following jobs are sequenced according to the SPT rule, then job B is completed on day (assume zero for today's date)

(Multiple Choice)
4.8/5
(34)

What is the difference between infinite and finite scheduling?

(Essay)
5.0/5
(32)

The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson's Rule is used to sequence the jobs, then Job A would complete processing on operation 2 at The following set of jobs must be processed serially through a two-step system. The times at each process are in hours. If Johnson's Rule is used to sequence the jobs, then Job A would complete processing on operation 2 at

(Multiple Choice)
4.8/5
(29)

The time required to complete a group of jobs is referred to as

(Multiple Choice)
4.8/5
(40)

Increasing the capacity of a work centre that is a bottleneck increases the output.

(True/False)
4.9/5
(37)

Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below: Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D). The times required in minutes for each product on each machine are shown below:   The minimum time required to complete all the products is The minimum time required to complete all the products is

(Multiple Choice)
4.8/5
(35)

If the following jobs are sequenced according to the FCFS rule, then the total number of jobs that would be late is (assume zero for today's date) If the following jobs are sequenced according to the FCFS rule, then the total number of jobs that would be late is (assume zero for today's date)

(Multiple Choice)
4.7/5
(35)

The sequencing rule that minimizes average tardiness for a set of jobs to be processed on one machine is

(Multiple Choice)
4.8/5
(36)

Who developed the theory of constraints (TOC) and what is its approach to scheduling?

(Essay)
4.9/5
(36)

If a job is ahead of schedule, then its critical ratio (CR) will be

(Multiple Choice)
4.9/5
(36)

Scheduling using the theory of constraints (TOC) requires that the process batch sizes and the transfer batch sizes always match.

(True/False)
4.9/5
(38)
Showing 21 - 40 of 96
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)