Exam 9: Project Management
Exam 1: Introduction to Operations and Supply Chain Management102 Questions
Exam 2: Quality Management88 Questions
Exam 3: Statistical Process Control157 Questions
Exam 4: Product Design95 Questions
Exam 5: Service Design91 Questions
Exam 6: Processes and Technology81 Questions
Exam 7: Capacity and Facilities Design128 Questions
Exam 8: Human Resources131 Questions
Exam 9: Project Management106 Questions
Exam 10: Supply Chain Management Strategy and Design72 Questions
Exam 11: Global Supply Chain Procurement and Distribution122 Questions
Exam 12: Forecasting92 Questions
Exam 13: Inventory Management127 Questions
Exam 14: Sales and Operations Planning123 Questions
Exam 15: Resource Planning97 Questions
Exam 16: Lean Systems88 Questions
Exam 17: Scheduling96 Questions
Select questions type
PERT stands for program enterprise and resource technique.
Free
(True/False)
4.8/5
(32)
Correct Answer:
False
A project consists of the following four activities with activity times in days: Table 9.2
- Using Table 9.2, the earliest finish (EF) time for activity C is

Free
(Multiple Choice)
4.8/5
(43)
Correct Answer:
C
Which of the following statements is generally true regarding the relationship between project crashing costs and indirect costs?
Free
(Multiple Choice)
5.0/5
(29)
Correct Answer:
D
Why have projects taken on a more crucial role in operations management?
(Essay)
4.9/5
(31)
A project consists of the following four activities with activity times in days: Table 9.2
-Using Table 9.2, the earliest start (ES) time for activity B is

(Multiple Choice)
4.8/5
(37)
The subjective estimate of the activity time that would most frequently occur if the activity were repeated many times is the
(Multiple Choice)
4.9/5
(37)
A project consists of the following activities: Table 9.1
-Using Table 9.1, the latest start (LS) time for activity B is

(Multiple Choice)
4.9/5
(29)
Activities that are not on a project's critical path have zero slack.
(True/False)
4.9/5
(27)
A ___ breaks down a project into components, subcomponents, activities, and tasks.
(Multiple Choice)
4.8/5
(38)
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the earliest finish time for activity C is

(Multiple Choice)
4.9/5
(25)
Develop and analyze a probabilistic activity time estimate network for a project.
(Essay)
4.9/5
(29)
A project consists of the following four activities with activity times in days: Table 9.2
-Using Table 9.2, the critical path for this project is

(Multiple Choice)
4.8/5
(34)
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the probability that the project will take longer than 33 weeks to complete is approximately

(Multiple Choice)
4.8/5
(41)
Asian cultures tend to embrace project management's methodical approach more than western cultures.
(True/False)
4.8/5
(30)
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
-Using Table 9.3, the variance of the project's total completion time is

(Multiple Choice)
4.9/5
(35)
Discuss the key elements of project control and define enterprise project management.
(Essay)
4.8/5
(35)
The key elements of project control includes all the following except
(Multiple Choice)
4.7/5
(38)
Issues of cultural diversity in project management should only be addressed if and when they arise.
(True/False)
4.9/5
(34)
The estimated mean time for an activity with a most likely time (m) equal to 12 weeks, an optimistic time (a) equal to 9 weeks, and a pessimistic time (b) equal to 18 weeks is
(Multiple Choice)
4.9/5
(37)
Showing 1 - 20 of 106
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)