Exam 13: Working With Projects
Exam 1: Operations Management and You71 Questions
Exam 2: Designing Products and Processes81 Questions
Exam 3: Process and Service Design79 Questions
Exam 4: Managing Processes79 Questions
Exam 5: Forecasting117 Questions
Exam 6: Capacity Planning82 Questions
Exam 7: Managing Capacity78 Questions
Exam 8: Managing Inventory98 Questions
Exam 9: Managing Quality101 Questions
Exam 10: Supply Chain Design87 Questions
Exam 11: Managing Supply Chains98 Questions
Exam 12: Finding the Right Location82 Questions
Exam 13: Working With Projects92 Questions
Select questions type
Very few big budget projects are failures because more money spent means quicker project completion.
(True/False)
4.8/5
(39)
Three key performance dimensions of a project are cost, scope, and time.
(True/False)
4.7/5
(33)
Short- to medium-term project selection with predictable cash flows can be done by which of the following methods?
(Multiple Choice)
4.8/5
(33)
Which of the following is the critical path for the project network shown in the following diagram? 

(Multiple Choice)
4.8/5
(31)
__________ a project involves reducing expected project activity times and adding more resources (people/tools) to it.
(Short Answer)
5.0/5
(41)
Activity times for a project can be estimated by all but which of the following methods?
(Multiple Choice)
4.8/5
(36)
__________ is the art of orchestrating time and resources to meet and manage stakeholder goals, project risks, and project changes.
(Short Answer)
4.8/5
(34)
Projects with larger and longer deliverables are becoming more popular because of the chance to generate more revenue for the project providers.
(True/False)
4.9/5
(35)
Commuting to work and maintaining a website are good examples of long-term projects.
(True/False)
4.8/5
(33)
Given the following activities, their durations, and the predecessor relationships, construct the network flow diagram and answer the questions that follow.
\begin{tabular}{|c|c|c|c|c|}
\hline Activity Description & Immediate Predecessor(s) & Optimistic (hours) & Most Likely (hours) & Pessimistic (hours) \\
\hline & - & 7 & 10 & 13 \\
\hline & & 5 & 11 & 23 \\
\hline & & 11 & 15 & 19 \\
\hline & & 4 & 5 & 6 \\
\hline & & 9 & 11 & 25 \\
\hline & & 5 & 6 & 7 \\
\hline & & 5 & 5 & 5 \\
\hline & & 9 & 11 & 13 \\
\hline & & 7 & 11 & 15 \\
\hline & & 4 & 5 & 6 \\
\hline
\end{tabular}
A) What is the expected time for activity E?
B) What is the variance for activity E?
C) What is the critical path based on the calculation of the estimated times?
D) What is the estimated duration of the critical path?
E) What is the estimated variance along the critical path?
F) What is the probability of completion of the project before hour 45?
(Essay)
4.9/5
(40)
Using the data supplied, what is the crashing cost per week for activity A?
(Multiple Choice)
4.9/5
(41)
Seeking improvement in any one dimension of project performance requires acceptance of levels of elevated performance on the others.
(True/False)
4.9/5
(30)
If the length of the critical path is 25 weeks, what is the probability that the project will be completed on or before 22 weeks?
(Multiple Choice)
4.8/5
(36)
Evaluation methods used for projects with cash flows that are too uncertain to estimate probabilities include the minimax, maximax, and the maximin regret.
(True/False)
4.8/5
(31)
Evaluation methods used for projects with predictable cash flows include the payback period, the NPV, the ROI, and the IRR.
(True/False)
4.9/5
(37)
The phase in which we hand over the final deliverables to the client and intimate formal project closure to all stakeholders is called project closure.
(True/False)
4.9/5
(48)
Showing 61 - 80 of 92
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)