Exam 13: Working With Projects
Exam 1: Operations Management and You71 Questions
Exam 2: Designing Products and Processes81 Questions
Exam 3: Process and Service Design79 Questions
Exam 4: Managing Processes79 Questions
Exam 5: Forecasting117 Questions
Exam 6: Capacity Planning82 Questions
Exam 7: Managing Capacity78 Questions
Exam 8: Managing Inventory98 Questions
Exam 9: Managing Quality101 Questions
Exam 10: Supply Chain Design87 Questions
Exam 11: Managing Supply Chains98 Questions
Exam 12: Finding the Right Location82 Questions
Exam 13: Working With Projects92 Questions
Select questions type
In the implementation phase, project details are thrashed out and documented.
Free
(True/False)
4.9/5
(37)
Correct Answer:
False
Using the data supplied in the following table, by how many weeks can we crash activity A? Activity Normal Time Crash Time Normal Cost Crash Cost Availab le Weeks of Crashing Crashing Cost/Week A 4 2 \ 15,000 \ 21,000 B 3 2 \ 15,000 \ 18,000 C 4 4 \ 9,000 \ 9,000 5 3 \ 10,000 \ 16,000 E 4 1 \ 10,000 \ 13,000 F 1 1 \ 10,000 \ 10,000
Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
D
Project teams are organized in a cross-functional or matrix structure.
Free
(True/False)
4.7/5
(36)
Correct Answer:
False
If we cannot estimate probabilities because the project cash flows are uncertain, then we can use all of the following methods except
(Multiple Choice)
4.9/5
(40)
Using the information shown in the previous table, what is the variance for activity H?
(Multiple Choice)
4.8/5
(41)
Lucy, the project manager, and her team were able to archive important project documents in a safe and accessible place and then celebrate during the __________ phase of the project.
(Short Answer)
4.8/5
(32)
If the length of the critical path is 25 weeks, what is the shortest project due date if the project manager wants at least a 98 percent probability that the project will be completed on or before the due date?
(Multiple Choice)
4.9/5
(33)
How would you describe the responsibilities of a project manager? Briefly describe these responsibilities for a team manager who is in charge of a team of four people for a semester-long project involving research and a 45-minute presentation.
(Essay)
4.8/5
(25)
Project management is the controlling of time and resources to meet and manage stakeholder goals, project risks, and project changes.
(True/False)
4.9/5
(40)
A full time equivalent is the number of hours it would take the project team to complete an activity.
(True/False)
4.8/5
(44)
The __________ is a statement of all work, tasks, and subtasks that have to be completed.
(Short Answer)
4.9/5
(34)
Popular techniques to plan for and monitor a project include
(Multiple Choice)
4.7/5
(28)
Using the data supplied, which activity should be crashed first if the critical path is A-B-D-E?
(Multiple Choice)
4.8/5
(37)
Draw the project network based on the following information. Identify all of the possible paths and the critical path, and calculate the project completion time. In addition, complete the following PERT table.
Activity Immediate Predecessor(s) Time (Minutes) - 5 - 6 8 11 8 , 8 , 10 , 11 Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack A B C D E F G H
(Essay)
4.9/5
(33)
Project management involves managing all of the following except
(Multiple Choice)
4.8/5
(37)
Critical activities are those activities where no delays can be tolerated.
(True/False)
4.9/5
(27)
Given that activity B has the following times, which of the following statements is true about activity B?
Earliest start time = 9 days; latest start time = 17 days; earliest finish time = 15 days; latest finish time = 23 days
(Multiple Choice)
4.8/5
(48)
Any activity that cannot be delayed without delaying the entire project has zero __________.
(Short Answer)
4.9/5
(38)
A project has three possible paths from start to finish. Path A-B-C is 15 hours; path A-C-D is 10 hours, and path A-C-E is 20 hours. Which one of the following statements is true?
(Multiple Choice)
4.9/5
(38)
Showing 1 - 20 of 92
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)