Exam 5: Project Execution and Closeout
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
Statement: Side items are extras and frills to the main end-item that are usually unnecessary.
Free
(True/False)
4.9/5
(30)
Correct Answer:
False
List three kinds of system conversion.
Free
(Short Answer)
4.8/5
(36)
Correct Answer:
parallel, phase-in, and immediate replacement (cold turkey)
Statement: Side-items are part of the environment of the project and for which project management has no responsibility.
Free
(True/False)
4.7/5
(26)
Correct Answer:
False
Which one of the following is true about project termination and close-out:
(Multiple Choice)
4.8/5
(23)
Strategies for system installation and conversion are (circle all that are correct)
(Multiple Choice)
4.8/5
(38)
Statement: The design stage includes detailed planning for the production/build stage.
(True/False)
4.7/5
(34)
Statement: System side-items are first identified and accounted for during project execution.
(True/False)
4.8/5
(35)
Statement: Phase D happens after the project has been completed and closed out
(True/False)
4.8/5
(35)
Statement: So that information is as current as possible, planning for implementation should begin during the implementation stage.
(True/False)
4.9/5
(41)
Statement: It is the sole responsibility of the customer to make sure all contractual items have been delivered, that all items are closed out, and that final payment has been made to the contractor.
(True/False)
4.9/5
(39)
Statement: The contractor may be required to pay compensation to the client if a product does not conform to specifications, even if the product has already been delivered and accepted by the customer.
(True/False)
4.9/5
(38)
Statement: A detailed plan for production is first prepared during the production stage.
(True/False)
4.9/5
(35)
Indicate below whether the following items are for a post completion project summary (S) or a post-installation system review (R):
a. ____ review project objectives and project life cycle
b. ____ determine if the system is doing what it was intended to do
c. ____ identify areas of good and poor performance on the part of the project team
d. ____ review project expenditures and profitability
e. ____ check for system design flaws and needed changes
f. ____ where necessary, suggest changes to procedures that would improve performance in similar, future projects.
(Short Answer)
4.8/5
(30)
What are the purposes of a post-completion project review (postmortem). Circle all that apply:
(Multiple Choice)
4.8/5
(27)
Statement: Prolonging the design stage to get the design right can ultimately reduce overall project cost and duration.
(True/False)
4.9/5
(29)
Statement: The majority of tests on a project end-item are performed after the item has been turned over to the customer / user.
(True/False)
4.8/5
(34)
Statement: The execution stage usually includes project conception and approval.
(True/False)
4.8/5
(35)
Statement: In the implementation stage, the user approves the design so the end-item system can be built.
(True/False)
4.8/5
(38)
Showing 1 - 20 of 32