Exam 6: Basic Project Planning Techniques
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
Procurement management can include which if the following (circle all that apply)
Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
A, B, C, D, E
For the next three questions, choose letters of the terms in the following list that best fit the questions.
Where (what section or method) in the project master plan are the following questions addressed (Note, some of these terms might also have applied to the above questions; these can be used again.) .
-What is the project all about; what does the project involve?
Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
D
Which of the following are essential elements of a project plan (circle one only):
Free
(Multiple Choice)
4.7/5
(32)
Correct Answer:
C
Statement: Procurement management refers to the management of items produced, or work done internally.
(True/False)
4.9/5
(32)
Statement: The statement of work is a concise description of the project and its deliverables.
(True/False)
4.8/5
(29)
For the next three questions, choose letters of the terms in the following list that best fit the questions.
-In addition to the above five, what are five other topics or areas often covered in the project plan:
(Multiple Choice)
4.8/5
(29)
Statement: Portions of or even entire work packages might fall under "procurement management."
(True/False)
4.7/5
(30)
For the next three questions, choose letters of the terms in the following list that best fit the questions.
Where (what section or method) in the project master plan are the following questions addressed (Note, some of these terms might also have applied to the above questions; these can be used again.) .
-How much will the project cost?
(Multiple Choice)
4.8/5
(32)
For the next three questions, choose letters of the terms in the following list that best fit the questions.
Where (what section or method) in the project master plan are the following questions addressed (Note, some of these terms might also have applied to the above questions; these can be used again.) .
-Who will be involved in or working on the project?
(Multiple Choice)
4.9/5
(39)
Scrutinize the chart below to answer questions 1 through 5:
1. How many "events" are shown? ______
2. How many "activities" are shown? ______
3. Which activity (if any) is (are) completed? ______
4. As of SD, which activity (if any) is (are) ahead of schedule? ______
5. As of SD, which activity (if any) is (are) behind schedule? ______

(Short Answer)
4.9/5
(40)
Statement: In a hierarchy of charts, top-level charts represent the entire project, lower-level charts represent smaller, shorter-term tasks within the project.
(True/False)
4.8/5
(36)
Statement: The schedule for procured items can be created independently of the project schedule.
(True/False)
4.9/5
(33)
Determining how far the breakdown on a WBS should go (circle one):
(Multiple Choice)
4.9/5
(28)
Statement: Task level and project level charts are both prepared by the same person, usually the project manager.
(True/False)
4.8/5
(28)
Procurement management refers to management of (circle all that apply)
(Multiple Choice)
5.0/5
(30)
Statement: Major areas of work that must be procured will be identified in the WBS.
(True/False)
4.9/5
(37)
Showing 1 - 20 of 32
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)