Exam 7: Project Schedule Planning and Networks

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The advantages of scheduling include all of the following EXCEPT:

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

C

If Activity A has to be performed before Activity B can start, then:

Free
(Multiple Choice)
4.8/5
(44)
Correct Answer:
Verified

A

Statement: Redundant activities are activities that are repetitive of others and can be deleted from the project.

Free
(True/False)
4.7/5
(42)
Correct Answer:
Verified

False

Use the following Gantt chart and table to answer questions (a) and (b). Use the following Gantt chart and table to answer questions (a) and (b).    (a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity.    (b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days.   (a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity. Use the following Gantt chart and table to answer questions (a) and (b).    (a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity.    (b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days.   (b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days. Use the following Gantt chart and table to answer questions (a) and (b).    (a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity.    (b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days.

(Short Answer)
4.9/5
(23)

The latest allowable finish time that an event can occur, LF, depends on:

(Multiple Choice)
4.9/5
(37)

In the PDM method (circle all that are true):

(Multiple Choice)
4.7/5
(25)

In a network, the critical path indicates:

(Multiple Choice)
4.7/5
(38)

The critical path:

(Multiple Choice)
4.8/5
(43)

The forward and backward pass:

(Multiple Choice)
4.7/5
(31)

If an activity has two immediate successors and their late start times are 26 and 33, respectively, then the late finish time of that activity must be:

(Multiple Choice)
4.8/5
(35)

Use the table and network below to answer parts (a) through (d). Activity Time (Weeks) Weekly Cost (\ K) Total (\ ) A 5 2 10 B 8 3 24 C 6 4 24 D 3 3 9 E 4 2 8 F 3 1 78  Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.     (a) On the network above, show ES, EF, LS, and LF for every event. (b) Below, construct a Gantt chart for the network using only ES's and EF's.  Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.     (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.  Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.     (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.  Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.

(Short Answer)
4.9/5
(38)

The early expected start time, ES, of an activity depends on the completion:

(Multiple Choice)
4.9/5
(38)

Statement: The term "dummy activity" is a misnomer since each dummy represents work, takes time, and requires use of resources.

(True/False)
4.7/5
(35)

Statement: If an activity has multiple predecessors, its late start is determined by the latest finish of its predecessors.

(True/False)
4.8/5
(32)

In a network, the critical path is that sequence of activities that requires:

(Multiple Choice)
4.8/5
(45)

Level the resources for the activities below: Level the resources for the activities below:      Level the resources for the activities below:

(Short Answer)
4.7/5
(35)

Which one of the following statements is true:

(Multiple Choice)
4.8/5
(46)

Doing a project fast has the following advantages:

(Multiple Choice)
4.9/5
(28)

Statement: The total slack of each of the activities on a subpath will be the same as the total slack of the other activities on the subpath.

(True/False)
4.9/5
(35)

Statement: The free slack of each of the activities on a subpath will be the same as the free slack of the other activities on the subpath.

(True/False)
4.8/5
(37)
Showing 1 - 20 of 26
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)