Exam 7: Project Schedule Planning and Networks
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
The advantages of scheduling include all of the following EXCEPT:
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
C
If Activity A has to be performed before Activity B can start, then:
Free
(Multiple Choice)
4.8/5
(44)
Correct Answer:
A
Statement: Redundant activities are activities that are repetitive of others and can be deleted from the project.
Free
(True/False)
4.7/5
(42)
Correct Answer:
False
Use the following Gantt chart and table to answer questions (a) and (b).
(a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity.
(b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days.




(Short Answer)
4.9/5
(23)
The latest allowable finish time that an event can occur, LF, depends on:
(Multiple Choice)
4.9/5
(37)
If an activity has two immediate successors and their late start times are 26 and 33, respectively, then the late finish time of that activity must be:
(Multiple Choice)
4.8/5
(35)
Use the table and network below to answer parts (a) through (d).
Activity Time (Weeks) Weekly Cost (\ K) Total (\ ) A 5 2 10 B 8 3 24 C 6 4 24 D 3 3 9 E 4 2 8 F 3 1 78
(a) On the network above, show ES, EF, LS, and LF for every event.
(b) Below, construct a Gantt chart for the network using only ES's and EF's.
(C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.
(d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.




(Short Answer)
4.9/5
(38)
The early expected start time, ES, of an activity depends on the completion:
(Multiple Choice)
4.9/5
(38)
Statement: The term "dummy activity" is a misnomer since each dummy represents work, takes time, and requires use of resources.
(True/False)
4.7/5
(35)
Statement: If an activity has multiple predecessors, its late start is determined by the latest finish of its predecessors.
(True/False)
4.8/5
(32)
In a network, the critical path is that sequence of activities that requires:
(Multiple Choice)
4.8/5
(45)
Statement: The total slack of each of the activities on a subpath will be the same as the total slack of the other activities on the subpath.
(True/False)
4.9/5
(35)
Statement: The free slack of each of the activities on a subpath will be the same as the free slack of the other activities on the subpath.
(True/False)
4.8/5
(37)
Showing 1 - 20 of 26
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)