Exam 8: Advanced Project Network Analysis and Scheduling
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
The following type of buffer does not add time to a schedule:
Free
(Multiple Choice)
4.9/5
(28)
Correct Answer:
D
Statement: The cost slope is the marginal tradeoff between the cost and time of doing a given activity.
(True/False)
5.0/5
(39)
Statement: Given the assumptions of PERT, it is possible to determine the probability that a project will be completed by a specified date.
(True/False)
5.0/5
(28)
To reduce the duration of a project using CPM, it is necessary to make a reduction on the activity with:
(Multiple Choice)
4.7/5
(33)
Statement: In the critical path method (CPM), the direct cost of an activity is assumed to be proportional to its time, so shortening it to its "crash" time reduces its cost.
(True/False)
4.7/5
(34)
Statement: It is relatively easy to level many resources in a project at the same time.
(True/False)
4.9/5
(31)
To find the shortest possible project duration for the least cost:
(Multiple Choice)
4.7/5
(36)
Statement: Although the times used in PERT are "estimates," the resulting probabilities are highly credible, especially in cases where little or no previous experience exists.
(True/False)
4.9/5
(36)
The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission.
-Consider the schedule below:
RB = Resource Buffer
FB = Feeding Buffer
PB = Project Buffer
The letters A, B, C, D and E represent the resources needed to do the indicated activities.
(a) Show the critical chain on the sketch above.
(b) Why is there no resource buffer (RB) before the activity to be performed by A?
(c) Why is there no resource buffer before the second task to be performed by resource B?
(d) Would the 6-day duration shown for the activity to be performed by A be a pessimistic or a realistic value?

(Essay)
4.8/5
(34)
An approach to accelerate a project by simply eliminating discretionary dependencies is called:
(Multiple Choice)
4.8/5
(38)
Statement: Indirect costs include administrative, overhead, and any penalty costs.
(True/False)
5.0/5
(37)
The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission.
-Complete the following table: state how the five steps of constraints management relate to the management of a single project when the critical chain method is used.
Constraints management step Application to management of a (single) project 1. Identify the constraint 2. Decide how to exploit the constraint(s) 3. Subordinate everything to the decision(s) in 2 above 4. Elevate the constraint(s) (in other words, take steps to "widen the bottleneck") 5. Go back to Step 1.
(Short Answer)
4.8/5
(38)
Statement: PERT requires three time estimates for every activity.
(True/False)
5.0/5
(39)
Use the following network diagram and table to answer parts (a) through (d).
Normal Crash Activity Time Cost Time Cost A 6 100 3 400 B 8 200 8 200 C 4 200 2 800 D 10 1000 5 4000 E 8 200 4 1000 F 10 1500 6 4500 G 8 800 5 1000
(a) Under "normal" conditions: what is the earliest the project can be completed; what is the critical path; what is the cost?
(b) Suppose you wanted to complete the project one week earlier than under normal conditions. What activity(ies) would you have to speed up. How much would it add to the cost of the project?
(c) Under "crash" conditions: what is the earliest the project can be completed; what is the minimum it will cost to complete it in this time.
(d) The costs in part (a) through (d) are direct costs. Suppose overhead costs are determined by the formula C = 4000 + 2000t, where t is the project duration in weeks. Using this formula, what are the total project costs (direct plus indirect) for the project durations you got in parts (a) and (d)? Based on a cost comparison, should the project be completed under normal conditions, crash conditions, or somewhere in between?

(Essay)
4.8/5
(36)
Statement: A "resource loading" chart shows the amount of a given resource required in a project over a specified period of time.
(True/False)
4.9/5
(34)
Which statement is correct: In the CPM, as the duration of a project is decreased, usually:
(Multiple Choice)
5.0/5
(33)
Showing 1 - 20 of 29
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)