Which of the following statements are true about cost estimating (circle all that are true):

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
Verified

B, C, D,

The project planning and estimating process (circle all that apply):

Free
(Multiple Choice)
4.8/5
(43)
Correct Answer:
Verified

A, B, C

Statement: The majority of a system's life cycle costs are determined by decisions made in the conceptual and early design stages.

Free
(True/False)
4.8/5
(28)
Correct Answer:
Verified

True

If the actual cost turns to be $234,000, which of the following is the most accurate estimate:

(Multiple Choice)
4.8/5
(32)

Which method provides the least accuracy when estimating total project cost (circle on):

(Multiple Choice)
4.7/5
(36)

Statement: A time-phased budget shows project costs budgeted over time according to project schedules.

(True/False)
4.9/5
(34)

Statement: The project cost estimate is derived from the project target cost.

(True/False)
4.8/5
(34)

A contingency amount can be (circle one):

(Multiple Choice)
4.8/5
(32)

The major problem with using traditional budgets for projects is that they:

(Multiple Choice)
4.8/5
(33)

Statement: The feasible budget region is developed by looking at the difference between the project cost profile using early start times and the profile using late start times.

(True/False)
4.7/5
(33)

Statement: Life cycle costs are the same as project costs.

(True/False)
4.7/5
(35)

The estimate providing the best accuracy for total project cost comes from (circle one):

(Multiple Choice)
4.9/5
(34)

Statement: The parametric method of cost estimating can be combined with the analogy method.

(True/False)
4.9/5
(37)

Statement: In general, high precision in an estimate is more important than high accuracy.

(True/False)
4.9/5
(42)

Which method relies on formulae and tables to estimate project costs (circle on):

(Multiple Choice)
4.7/5
(32)

Statement: The net present worth of the project derived from project expenses can be increased by delaying the start of project activities.

(True/False)
4.8/5
(36)

Statement: When we speak of recurring costs, we usually associate these costs with one-of-kind or first-of-a-kind items.

(True/False)
4.8/5
(44)

Statement: If a cost estimate comes up too high, a good way to reduce it is to uniformly cut costs by a certain percentage for everything on the project.

(True/False)
4.8/5
(36)

Statement: Generally the amount needed in the management reserve should decrease as the project progress.

(True/False)
4.8/5
(25)

Statement: The process of breaking the project into work packages through the WBS has no relevancy to cost estimating.

(True/False)
5.0/5
(28)