Exam 9: Cost Estimating and Budgeting
Exam 1: What Is Project Management12 Questions
Exam 2: Systems Approach28 Questions
Exam 3: Project Life Cycle and Project Conception32 Questions
Exam 4: Project Definition and System Definition42 Questions
Exam 5: Project Execution and Closeout32 Questions
Exam 6: Basic Project Planning Techniques32 Questions
Exam 7: Project Schedule Planning and Networks26 Questions
Exam 8: Advanced Project Network Analysis and Scheduling29 Questions
Exam 9: Cost Estimating and Budgeting29 Questions
Exam 10: Project Quality Management11 Questions
Exam 11: Project Risk Management31 Questions
Exam 12: Project Procurement Management and Contracting36 Questions
Exam 13: Project Monitoring and Control41 Questions
Exam 14: Agile Project Management and Lean27 Questions
Exam 15: Project Organizational Structure and Integration22 Questions
Exam 16: Project Roles and Stakeholders22 Questions
Exam 17: Leadership, Teamwork, and Conflict30 Questions
Exam 18: Meta-Management of Projects and Program Management38 Questions
Exam 19: Project Selection and Portfolio Management40 Questions
Exam 20: International Project Management45 Questions
Select questions type
Which of the following statements are true about cost estimating (circle all that are true):
Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
B, C, D,
The project planning and estimating process (circle all that apply):
Free
(Multiple Choice)
4.8/5
(43)
Correct Answer:
A, B, C
Statement: The majority of a system's life cycle costs are determined by decisions made in the conceptual and early design stages.
Free
(True/False)
4.8/5
(28)
Correct Answer:
True
If the actual cost turns to be $234,000, which of the following is the most accurate estimate:
(Multiple Choice)
4.8/5
(32)
Which method provides the least accuracy when estimating total project cost (circle on):
(Multiple Choice)
4.7/5
(36)
Statement: A time-phased budget shows project costs budgeted over time according to project schedules.
(True/False)
4.9/5
(34)
Statement: The project cost estimate is derived from the project target cost.
(True/False)
4.8/5
(34)
The major problem with using traditional budgets for projects is that they:
(Multiple Choice)
4.8/5
(33)
Statement: The feasible budget region is developed by looking at the difference between the project cost profile using early start times and the profile using late start times.
(True/False)
4.7/5
(33)
The estimate providing the best accuracy for total project cost comes from (circle one):
(Multiple Choice)
4.9/5
(34)
Statement: The parametric method of cost estimating can be combined with the analogy method.
(True/False)
4.9/5
(37)
Statement: In general, high precision in an estimate is more important than high accuracy.
(True/False)
4.9/5
(42)
Which method relies on formulae and tables to estimate project costs (circle on):
(Multiple Choice)
4.7/5
(32)
Statement: The net present worth of the project derived from project expenses can be increased by delaying the start of project activities.
(True/False)
4.8/5
(36)
Statement: When we speak of recurring costs, we usually associate these costs with one-of-kind or first-of-a-kind items.
(True/False)
4.8/5
(44)
Statement: If a cost estimate comes up too high, a good way to reduce it is to uniformly cut costs by a certain percentage for everything on the project.
(True/False)
4.8/5
(36)
Statement: Generally the amount needed in the management reserve should decrease as the project progress.
(True/False)
4.8/5
(25)
Statement: The process of breaking the project into work packages through the WBS has no relevancy to cost estimating.
(True/False)
5.0/5
(28)
Showing 1 - 20 of 29
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)