Exam 13: Project Monitoring and Control

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Statement: A single-value estimate of the completion time or cost (EAC) accounts for the uncertainty in the project EV estimate.

Free
(True/False)
4.8/5
(31)
Correct Answer:
Verified

False

Statement: Project control primarily involves monitoring performance, comparing performance to standards, and taking necessary corrective action.

Free
(True/False)
4.8/5
(42)
Correct Answer:
Verified

True

Which of the following are true about formal project review meetings (circle all that apply):

Free
(Multiple Choice)
4.8/5
(25)
Correct Answer:
Verified

B, D

Ways to control the adverse impact of changes in a project include (circle all that apply):

(Multiple Choice)
4.7/5
(34)

Match the following formulas with their appropriate performance measures. -EV/AC

(Multiple Choice)
4.8/5
(35)

Statement: The number of changes made during a project can often be reduced through better planning in the early stages.

(True/False)
4.7/5
(32)

To implement a time buffer (circle one):

(Multiple Choice)
4.8/5
(33)

Among important ways to assess the status of a project are (circle all that apply):

(Multiple Choice)
4.8/5
(31)

How or where is work progress measured (circle all that apply):

(Multiple Choice)
4.8/5
(37)

Match the following formulas with their appropriate performance measures. -EV - AC

(Multiple Choice)
4.7/5
(27)

Use the following information to perform an earned value analysis. Use the following information to perform an earned value analysis.    Summary analysis, as of Status Date a. Complete the PV column. b. Complete the EV column. c. What is the value of the work remaining on the project? d. What is the CPI as of the status date? e. Given the value of the work remaining and the CPI, what is the estimated cost to complete the project? f. Given the actual cost as of the status date and estimated cost to complete, what is the estimated cost at completion? Summary analysis, as of "Status Date" a. Complete the PV column. b. Complete the EV column. c. What is the value of the work remaining on the project? d. What is the CPI as of the status date? e. Given the value of the work remaining and the CPI, what is the estimated cost to complete the project? f. Given the actual cost as of the status date and estimated cost to complete, what is the estimated cost at completion?

(Essay)
4.9/5
(34)

Statement: To reduce confusion and increase the accuracy of work progress assessment, it is better to use one method of assessment rather than several.

(True/False)
4.8/5
(42)

About the project control process (circle all that apply):

(Multiple Choice)
5.0/5
(28)

Suppose a project was originally estimated to cost $100,000, and as of a given date the EV is $80,000 and the CPI is 0.80. What is the forecast cost to complete the project?

(Multiple Choice)
4.8/5
(30)

Statement: By monitoring performance indexes and variances at the project level only, it is possible to determine if everything is going well in the project.

(True/False)
4.8/5
(47)

Statement: Quality control in projects begins with creating a quality management plan.

(True/False)
4.8/5
(35)

Which of the following might project managers employ to reduce schedule overruns? (circle all that apply):

(Multiple Choice)
4.8/5
(28)

Statement: Project planning and project control are independent and unrelated functions.

(True/False)
4.8/5
(27)

Technical Performance Measurement (TPM) provides (circle all that apply):

(Multiple Choice)
4.8/5
(34)

Statement: A plus sign (+) before a schedule performance index (SPI) means that work is running ahead of schedule and a minus sign (-) before a cost performance index (CPI) means that the work is running over budget.

(True/False)
4.9/5
(32)