Possible decision alternatives found in capacity EMV problems are future demands or market favorability.

(True/False)
4.7/5
(40)

Christopher's Cranks uses a machine that can produce 100 cranks per hour. The firm operates 12 hours per day, five days per week. Due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 95% of the available time. Based on experience with other products, the firm expects to achieve an efficiency level for the cranks of 85%. What is the expected weekly output of cranks for this company?

(Multiple Choice)
4.8/5
(37)

Which of the following represents a common way to manage capacity in the service sector?

(Multiple Choice)
4.8/5
(36)

The capacity planning strategy that delays adding capacity until capacity is below demand, then adds a capacity increment so that capacity is above demand, is said to__________ demand.

(Short Answer)
4.9/5
(40)

The Academic Computing Center has five trainers available in its computer labs to provide training sessions to students. Assume that the design capacity of the system is 1900 students per semester and that effective capacity equals 90% of design capacity. If the number of students who actually got their orientation session is 1500, what is the efficiency of the system?

(Multiple Choice)
4.9/5
(39)

The local convenience store makes personal pan pizzas. Currently, their oven can produce 50 pizzas per hour. It has a fixed cost of $2,000, and a variable cost of $0.25 per pizza. The owner is considering a bigger oven that can make 75 pizzas per hour. It has a fixed cost of $3,000, but a variable cost of $0.20 per pizza. a. At what quantity do the two ovens have equal costs? b. If the owner expects to sell 9,000 pizzas, should he get the new oven?

(Essay)
4.8/5
(39)

Break-even is the number of units at which

(Multiple Choice)
4.8/5
(38)

Health Care Systems of the South is about to buy an expensive piece of diagnostic equipment. The company estimates that it will generate uniform revenues of $500,000 for each of the next eight years. What is the present value of this stream of earnings, at an interest rate of 6%? What is the present value if the machine lasts only six years, not eight? If the equipment cost $2,750,000, should the company purchase it?

(Essay)
4.9/5
(40)

A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the process time of the system?

(Multiple Choice)
4.8/5
(43)

One limitation of the net present value approach to investments is that investments with identical net present values may have very different cash flows.

(True/False)
4.7/5
(32)

__________ is the amount a facility can hold, store, receive, or produce in a period of time.

(Short Answer)
4.9/5
(40)

A product is currently made in a process-focused shop, where fixed costs are $9,000 per year and variable cost is $50 per unit. The firm sells the product for $200 per unit. What is the break-even point for this operation? What is the profit (or loss) on a demand of 200 units per year?

(Essay)
4.8/5
(39)

Utilization will always be lower than efficiency because

(Multiple Choice)
4.8/5
(40)

Net present value

(Multiple Choice)
4.8/5
(39)

A common method used to increase capacity with a lag strategy is

(Multiple Choice)
5.0/5
(31)

The staff training center at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 1200 employees per year. Since the training center was first put in use, the program has become more complex, so that 1050 now represents the most employees that can be trained per year. In the past year, 950 employees were trained. The efficiency of this system is approximately __________ and its utilization is approximately __________.

(Multiple Choice)
4.8/5
(38)

An assembly line has 10 stations with process times of 1, 2, 3, 4, …, 10 respectively. The process time of the system is

(Multiple Choice)
4.8/5
(28)

Multiproduct break-even analysis calculates the __________ of each product, __________ it in proportion to each product's share of total sales.

(Short Answer)
4.8/5
(29)

A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each, and only 400 trucks were repaired. What are the utilization and efficiency of the repair shop?

(Essay)
4.9/5
(36)

An organization whose capacity is on that portion of the average unit cost curve that falls as output rises

(Multiple Choice)
4.9/5
(36)