Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, the crash cost per period is

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

A

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day (rounded to nearest day).

Free
(Multiple Choice)
4.8/5
(24)
Correct Answer:
Verified

B

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is

Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
Verified

B

The phases of project management are

(Multiple Choice)
4.7/5
(30)

Describe the differences between a Gantt chart and a PERT/CPM network.

(Essay)
4.9/5
(37)

Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?

(Multiple Choice)
4.8/5
(44)

Shortening the project's duration by deleting unnecessary activities is called "project crashing."

(True/False)
4.8/5
(30)

__________ is an organization formed to ensure that programs (projects) receive the proper management and attention.

(Short Answer)
5.0/5
(30)

Which of the following statements about Bechtel is true?

(Multiple Choice)
5.0/5
(30)

A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance -- 7 9 14 1.361 2 2 8 0 8 12 16 0 3 5 10 1.361 4 6 8 0 6 8 10 0 , 2 3 4 0 2 2 8 1.000 6 8 16 2.778 , 4 6 14 2.778 , 2 2 5 0.250 a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. b. Which activities form the critical path? c. What is the estimated time of the critical path? d. What are the project variance and the project standard deviation? e. What is the probability of completion of the project after week 40?

(Essay)
4.8/5
(39)

What are the earliest activity start time and latest activity start time, and how are they computed?

(Essay)
4.7/5
(25)

Which of the following statements regarding Gantt charts is true?

(Multiple Choice)
4.8/5
(33)

Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day __________.

(Multiple Choice)
4.8/5
(29)

What is a project organization?

(Essay)
5.0/5
(37)

Which of these statements regarding time-cost tradeoffs in CPM networks is true?

(Multiple Choice)
4.8/5
(35)

Identify, in order, the six steps basic to both PERT and CPM.

(Essay)
4.8/5
(41)

Given the project within the table below calculate a. The critical path b. The minimum project duration c. The amount of slack for each activity Activity Duration (hours) Immediate Predecessors 4 None 3 None 10 None 7 , 1 1 5 ,

(Essay)
4.9/5
(34)

Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic -- 15 10 8 -- 9 8 7 10 6 5 3 3 3 , 9 5 1 , 10 7 4 , 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer than 30 time units.

(Essay)
4.9/5
(36)

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

(True/False)
4.7/5
(42)

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is

(Multiple Choice)
4.8/5
(43)
Showing 1 - 20 of 123
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)