Exam 3: Project Management
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management123 Questions
Exam 4: Forecasting144 Questions
Exam 5: Design of Goods and Services137 Questions
Exam 6: Managing Quality130 Questions
Exam 7: Statistical Process Control154 Questions
Exam 8: Process Strategy131 Questions
Exam9: Capacity and Constraint Management107 Questions
Exam 10: Location Strategies140 Questions
Exam 11: Layout Strategies161 Questions
Exam 12: Human Resources, Job Design, and Work Measurement191 Questions
Exam 13: Supply-Chain Management145 Questions
Exam 14: Outsourcing as a Supply-Chain Strategy73 Questions
Exam 15: Inventory Management155 Questions
Exam 16: Aggregate Planning134 Questions
Exam 17: Material Requirements Planning MRP and ERP169 Questions
Exam 18: Short-Term Scheduling139 Questions
Exam 19: Just-In-Time and Lean Options137 Questions
Exam 20: Maintenance and Reliability130 Questions
Exam 21: Decision-Making Tools97 Questions
Exam 22: Linear Programming100 Questions
Exam 23: Transportation Models94 Questions
Exam 24: Waiting-Line Models135 Questions
Exam 25: Learning Curves111 Questions
Exam 26: Simulation93 Questions
Select questions type
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, the crash cost per period is
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
A
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day (rounded to nearest day).
Free
(Multiple Choice)
4.8/5
(24)
Correct Answer:
B
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is
Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
B
Describe the differences between a Gantt chart and a PERT/CPM network.
(Essay)
4.9/5
(37)
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
(Multiple Choice)
4.8/5
(44)
Shortening the project's duration by deleting unnecessary activities is called "project crashing."
(True/False)
4.8/5
(30)
__________ is an organization formed to ensure that programs (projects) receive the proper management and attention.
(Short Answer)
5.0/5
(30)
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance -- 7 9 14 1.361 2 2 8 0 8 12 16 0 3 5 10 1.361 4 6 8 0 6 8 10 0 , 2 3 4 0 2 2 8 1.000 6 8 16 2.778 , 4 6 14 2.778 , 2 2 5 0.250
a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?
e. What is the probability of completion of the project after week 40?
(Essay)
4.8/5
(39)
What are the earliest activity start time and latest activity start time, and how are they computed?
(Essay)
4.7/5
(25)
Which of the following statements regarding Gantt charts is true?
(Multiple Choice)
4.8/5
(33)
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day __________.
(Multiple Choice)
4.8/5
(29)
Which of these statements regarding time-cost tradeoffs in CPM networks is true?
(Multiple Choice)
4.8/5
(35)
Given the project within the table below calculate
a. The critical path
b. The minimum project duration
c. The amount of slack for each activity
Activity Duration (hours) Immediate Predecessors 4 None 3 None 10 None 7 , 1 1 5 ,
(Essay)
4.9/5
(34)
Consider the network described in the table below.
Activity Immediate Predecessor(s) Pessimistic Probable Optimistic -- 15 10 8 -- 9 8 7 10 6 5 3 3 3 , 9 5 1 , 10 7 4 , 10 8 3
a. Calculate the expected duration of each activity.
b. Calculate the expected duration and variance of the critical path.
c. Calculate the probability that the project will be completed in fewer than 30 time units.
(Essay)
4.9/5
(36)
The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.
(True/False)
4.7/5
(42)
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is
(Multiple Choice)
4.8/5
(43)