Exam 10: learning curve– Static

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A job will have a learning rate of 75 percent. If the third unit requires 10 hours, the 12th unit should require about this many hours:

(Multiple Choice)
4.8/5
(32)

Suppose the first unit of output required 900 labor hours, and the second unit required only 810. At this rate, how many more units must be produced before labor requirements are less than 700 hours?

(Multiple Choice)
4.9/5
(37)

Which one of the following would learning curves probably affect the least?

(Multiple Choice)
4.9/5
(43)

In which of the following scenarios would an 80 percent learning curve be especially relevant?

(Multiple Choice)
4.8/5
(38)

The learning curve principle would apply to the number of students in a class: a class twice as large will learn 80 percent faster.

(True/False)
4.9/5
(30)

How long would a job with a 70 percent learning curve and a time of 20 hours for the first unit require (approximately, in hours) for the third unit?

(Multiple Choice)
4.7/5
(27)

A job has a 70 percent learning curve. If the first unit took 10 hours to complete, the third unit should take roughly how many hours?

(Multiple Choice)
4.7/5
(32)

For an 80 percent learning curve, if the first unit requires 10 hours, the second unit will require 8 hours and the third 6.4 hours.

(True/False)
4.8/5
(36)

According to learning curve theory, the time reduction per unit decreases (improves) as the number of units increases.

(True/False)
4.8/5
(35)

If we have never made the first unit but only think we know how much the labor time will be, we cannot draw a learning curve.

(True/False)
4.8/5
(29)

A job has an 80 percent learning curve. If the first unit took 50 hours to complete, the third unit should take roughly how many hours?

(Multiple Choice)
4.9/5
(35)

When are learning curves most relevant to managerial decision making in mass production settings?

(Multiple Choice)
4.8/5
(28)

A learning percentage of 95 percent indicates greater learning than a percentage of 90 percent.

(True/False)
4.9/5
(36)

Which of the following is not a major caution or criticism of learning curves?

(Multiple Choice)
4.8/5
(28)

Negotiated purchasing results in lower unit costs for smaller quantities.

(True/False)
4.7/5
(34)

A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours respectively. What is the appropriate learning curve?

(Multiple Choice)
4.7/5
(43)

A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours. If a contract for 30 units is canceled after the first 20 units, approximately how much of the expected total direct labor will have been expended to that point?

(Multiple Choice)
4.9/5
(24)

A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data: UNIT PRODUCED TIME REQUIRED Second 5 hours Fourth 4 hours What is the learning curve percentage?

(Multiple Choice)
4.8/5
(30)

When the task is fairly complex and has a longer duration, it will take a larger number of repetitions before improvement is observed.

(True/False)
5.0/5
(38)

A job is expected to have a learning curve of 90 percent. The third unit required 16 hours. The 12th unit should take approximately how many hours?

(Multiple Choice)
4.9/5
(28)
Showing 21 - 40 of 61
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)