Exam 10: learning curve– Static
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness70 Questions
Exam 3: Forecasting139 Questions
Exam 4: Product and Service Design78 Questions
Exam 4: RELIABILITY – Static12 Questions
Exam 6: Strategic Capacity Planning for Products and Services85 Questions
Exam 7: Decision Theory– Static114 Questions
Exam 8: Process Selection and Facility Layout132 Questions
Exam 9: Work Design and Measurement129 Questions
Exam 10: learning curve– Static61 Questions
Exam 11: Location Planning and Analysis62 Questions
Exam 12: The Transportation Model– Static20 Questions
Exam 13: Management of Quality97 Questions
Exam 14: Quality Control112 Questions
Exam 15: Acceptance Sampling– Static51 Questions
Exam 16: Aggregate Planning and Master Scheduling74 Questions
Exam 17: MRP and ERP81 Questions
Exam 18: Inventory Management128 Questions
Exam 19: JIT and Lean Operations79 Questions
Exam 20: Maintenance– Static36 Questions
Exam 21: Supply Chain Management87 Questions
Exam 22: Scheduling98 Questions
Exam 23: Project Management113 Questions
Exam 24: Management of Waiting Lines64 Questions
Exam 25: Linear Programming93 Questions
Select questions type
To which of the following challenges are learning curves important considerations?
(Multiple Choice)
4.9/5
(40)
According to learning curve theory, for certain kinds of tasks the cost per unit decreases as the number of repetitions increases.
(True/False)
5.0/5
(24)
The learning curve principle would apply to a baseball pitcher learning to throw a curveball.
(True/False)
4.9/5
(33)
Learning curves are used primarily for mass production applications.
(True/False)
4.9/5
(39)
A job has an 80 percent learning curve. The second unit required 12 hours to complete. Approximately how many hours will be devoted to the first five units (including those already completed)?
(Multiple Choice)
4.7/5
(30)
If the elapsed time for the task is short and the activity is somewhat routine, a modest amount of improvement occurs during the first few repetitions.
(True/False)
4.8/5
(40)
A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours.
Which unit, if any, will require approximately one-half the time of the first unit?
(Multiple Choice)
4.8/5
(32)
A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:
Approximately how long will it take to produce the fifth through tenth units?

(Multiple Choice)
4.9/5
(27)
Learning curves generally apply to situations in which there is a high degree of human involvement and tasks are fairly repetitive.
(True/False)
4.9/5
(30)
A job has an 80 percent learning curve. If the first unit took 40 hours to complete, the fourth unit should take roughly how many hours?
(Multiple Choice)
4.7/5
(40)
A manager is trying to estimate the learning rate for a new job. The first unit took 16 hours and the fourth unit required about 13 hours. The learning rate is:
(Multiple Choice)
5.0/5
(35)
A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data: UNIT PRODUCED TIME REQUIRED Second 5 hours Fourth 4 hours
Approximately how long will it take to produce the 10th unit?
(Multiple Choice)
4.8/5
(36)
Once production is underway and the learning curve effect is occurring, successive changes made to the production process will cause the time per unit to:
(Multiple Choice)
4.8/5
(39)
The fact that human activities typically improve when they are done on a repetitive basis is described by a(n):
(Multiple Choice)
4.7/5
(33)
In which of the following managerial activities would learning curves probably be the least useful?
(Multiple Choice)
4.8/5
(34)
Suppose the first unit required 800 hours and the second unit required only 680. Which of the following times for the fourth unit would be consistent with a true learning curve scenario?
(Multiple Choice)
4.9/5
(37)
An 80 percent learning curve means that with each doubling of repetitions there will be a 20 percent decrease in time per unit.
(True/False)
4.7/5
(35)
A company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours.
Approximately how long will it take to produce the 25th through 30th units?
(Multiple Choice)
4.8/5
(32)
The more __________ a task, the less likely it is that a substantial learning curve will be in effect.
(Multiple Choice)
4.7/5
(37)
Showing 41 - 60 of 61
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)