Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management
Exam 1: An Introduction to Project, program, and Portfolio Management75 Questions
Exam 2: Project, program, and Portfolio Selection75 Questions
Exam 3: Initiating Projects75 Questions
Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management100 Questions
Exam 5: Planning Projects, part 2 Project Quality, human Resource, communications, risk, and Procurement Management92 Questions
Exam 6: Executing Projects96 Questions
Exam 7: Monitoring and Controlling Projects90 Questions
Exam 8: Closing Projects and Best Practices50 Questions
Select questions type
Planning includes tasks related to each of the ____ project management knowledge areas.
(Multiple Choice)
4.9/5
(40)
____________________ modeling uses project characteristics (parameters)in a mathematical model to estimate project costs.
(Short Answer)
4.9/5
(47)
____________________ is the number of workdays or work hours required to complete a task.
(Short Answer)
4.9/5
(39)
Duration estimates are provided as a ____ number,such as four weeks; as a range,such as three to five weeks; or as a three-point estimate.
(Multiple Choice)
4.8/5
(41)
A(n)____________________ is a starting point,a measurement,or an observation that is documented so that it can be used for future comparison.
(Short Answer)
4.7/5
(33)
The main disadvantage of ____ is that it can end up lengthening the project schedule,because starting some tasks too soon often increases project risk and results in rework.
(Multiple Choice)
4.8/5
(26)
After defining project activities,the next step in project time management is activity ____.
(Multiple Choice)
4.9/5
(49)
Explain why project management plans need to be dynamic,flexible,and receptive to change when the environment or project changes.
(Essay)
4.9/5
(40)
The precedence diagramming method uses only finish-to-start dependencies.
(True/False)
4.9/5
(41)
The project manager should work with his or her team and ____ to determine the level of detail needed in the WBS dictionary.
(Multiple Choice)
4.8/5
(40)
It is poor practice to use more than one approach for creating a cost estimate.
(True/False)
4.9/5
(40)
The PMBOK Guide lists over ____ documents that project teams can produce as part of project planning.
(Multiple Choice)
4.8/5
(36)
The activity ____________________ is a tabulation of activities to be included on a project schedule.
(Short Answer)
4.8/5
(42)
Activity ____ provide schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.
(Multiple Choice)
4.9/5
(40)
____________________ is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.
(Short Answer)
4.9/5
(48)
A(n)____ path for a project is the series of activities that determine the earliest time by which the project can be completed.
(Multiple Choice)
4.9/5
(35)
Project management ____ facilitate communication among stakeholders and provide a baseline for progress measurement and project control.
(Multiple Choice)
4.9/5
(42)
Fast ____________________ involves doing activities in parallel that you would normally do in sequence.
(Short Answer)
4.7/5
(35)