Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Project ____ management includes the processes required to ensure that a project team completes a project within an approved budget.

(Multiple Choice)
4.8/5
(36)

____ includes the actual amount of time spent working on an activity plus elapsed time.

(Multiple Choice)
4.8/5
(33)

A work ____________________ is a task at the lowest level of the WBS.

(Short Answer)
4.9/5
(43)

Activity sequencing involves reviewing the activity list and attributes,project scope statement,and milestone list to determine the relationships or dependencies between activities.

(True/False)
4.8/5
(38)

As more information becomes available and decisions are made related to project scope,the project team should update the project scope statement.

(True/False)
4.7/5
(31)

The project team should review an activity list and activity attributes with project stakeholders.

(True/False)
4.9/5
(29)

What is the PERT weighted average based on an optimistic estimate of six days,a most likely estimate of eight days,and a pessimistic time of twelve days?

(Multiple Choice)
4.7/5
(45)

People are more likely to perform well if they know what they are supposed to do and when.

(True/False)
4.8/5
(33)

In an AOA network diagram,a(n)____ occurs when two or more nodes precede a single node.

(Multiple Choice)
4.8/5
(36)

The main output of scope definition is the scope ____________________.

(Short Answer)
4.9/5
(37)

There is usually no cost or duration associated with a milestone.

(True/False)
4.8/5
(26)

The format of the WBS dictionary can vary based on project needs.

(True/False)
4.9/5
(36)

Project ____ management involves coordinating all the project management knowledge areas throughout a project's life span.

(Multiple Choice)
4.9/5
(37)

The Just-In-Time Training project team decided to use the project management process groups for the level ____ tasks in its WBS.

(Multiple Choice)
4.8/5
(36)

Discretionary dependencies are defined by the project team.

(True/False)
4.9/5
(35)

____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.

(Multiple Choice)
4.8/5
(38)

The project manager monitors and controls work packages at the lowest level of the WBS.

(True/False)
5.0/5
(29)

A WBS ____________________ is a document that describes WBS tasks in detail.

(Short Answer)
4.7/5
(28)

There can be more than one critical path on a project.

(True/False)
4.9/5
(44)

Duration relates to the time estimate,not the effort estimate.

(True/False)
5.0/5
(37)
Showing 21 - 40 of 100