Exam 8: Project Scheduling
Exam 1: Projects and Project Management80 Questions
Exam 2: Process and Methods80 Questions
Exam 3: Project Management Tools80 Questions
Exam 4: Project Initiation80 Questions
Exam 5: Project Planning80 Questions
Exam 6: Risk Management80 Questions
Exam 7: Quality, Performance and Value80 Questions
Exam 8: Project Scheduling80 Questions
Exam 9: Resources, Costing, and Control80 Questions
Exam 10: Project Closure80 Questions
Exam 11: Project Organizational Structures80 Questions
Exam 12: Project Success80 Questions
Select questions type
A scheduling approach driven by dates and deadlines best describes
(Multiple Choice)
4.9/5
(34)
When using project management software,what are six factors that drive the calculation of time?
(Essay)
4.8/5
(30)
An activity on the critical path has several days of free float.
(True/False)
4.8/5
(43)
The ratio of rise and run of the project crash line describes
(Multiple Choice)
4.9/5
(32)
A specific task,or set of tasks,that is part of the scope of a project,uses up some of the resources of a project,and requires some finite time to be completed best defines
(Multiple Choice)
4.9/5
(36)
Multitasking is when a resource is responsible for doing more than one activity at the same time.
(True/False)
4.8/5
(40)
Which of the following was developed by Du Pont de Nemours & Co.and Remington Rand Corporation?
(Multiple Choice)
4.9/5
(45)
In CCPM,a finite amount of time that can be added to a sequence of activities to non-critical tasks best describes
(Multiple Choice)
4.9/5
(38)
Free float is an early warning and an indicator that corrective measures to scheduling have to be taken.
(True/False)
4.9/5
(34)
The shortest time an activity can be completed assuming a reasonable level of resources best defines
(Multiple Choice)
4.8/5
(39)
A technique to shorten the duration of a project to meet the target dates best describes
(Multiple Choice)
4.9/5
(38)
Which of the following demands extensive hardware,is used by larger organizations,and may not be ideal for managers working with smaller projects?
(Multiple Choice)
4.7/5
(42)
Before any successor activity can be initiated in PDM,all the activities that precede that activity have to be completed.
(True/False)
4.9/5
(41)
The earliest finish time is the total of the earliest start time and the activity duration.
(True/False)
4.9/5
(34)
PDM uses time as a common factor to analyze other project success factors like scope,resources,cost,performance,and value.
(True/False)
4.8/5
(33)
When working with project management software,factors that drive the calculation of time include each of the following except
(Multiple Choice)
4.8/5
(40)
The shortest time in which an activity can be completed best defines
(Multiple Choice)
4.9/5