Exam 8: Project Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A scheduling approach driven by dates and deadlines best describes

(Multiple Choice)
4.9/5
(34)

When using project management software,what are six factors that drive the calculation of time?

(Essay)
4.8/5
(30)

An activity on the critical path has several days of free float.

(True/False)
4.8/5
(43)

Shortening an activity is called

(Multiple Choice)
4.8/5
(42)

The ratio of rise and run of the project crash line describes

(Multiple Choice)
4.9/5
(32)

A specific task,or set of tasks,that is part of the scope of a project,uses up some of the resources of a project,and requires some finite time to be completed best defines

(Multiple Choice)
4.9/5
(36)

Multitasking is when a resource is responsible for doing more than one activity at the same time.

(True/False)
4.8/5
(40)

Causing a delay to a subsequent activity is called

(Multiple Choice)
4.9/5
(38)

Advantages of PERT include

(Multiple Choice)
4.7/5
(37)

Which of the following was developed by Du Pont de Nemours & Co.and Remington Rand Corporation?

(Multiple Choice)
4.9/5
(45)

In CCPM,a finite amount of time that can be added to a sequence of activities to non-critical tasks best describes

(Multiple Choice)
4.9/5
(38)

Free float is an early warning and an indicator that corrective measures to scheduling have to be taken.

(True/False)
4.9/5
(34)

The shortest time an activity can be completed assuming a reasonable level of resources best defines

(Multiple Choice)
4.8/5
(39)

A technique to shorten the duration of a project to meet the target dates best describes

(Multiple Choice)
4.9/5
(38)

Which of the following demands extensive hardware,is used by larger organizations,and may not be ideal for managers working with smaller projects?

(Multiple Choice)
4.7/5
(42)

Before any successor activity can be initiated in PDM,all the activities that precede that activity have to be completed.

(True/False)
4.9/5
(41)

The earliest finish time is the total of the earliest start time and the activity duration.

(True/False)
4.9/5
(34)

PDM uses time as a common factor to analyze other project success factors like scope,resources,cost,performance,and value.

(True/False)
4.8/5
(33)

When working with project management software,factors that drive the calculation of time include each of the following except

(Multiple Choice)
4.8/5
(40)

The shortest time in which an activity can be completed best defines

(Multiple Choice)
4.9/5
(37)
Showing 41 - 60 of 80
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)