Exam 8: Project Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Dependencies defined by the project team are

(Multiple Choice)
4.7/5
(33)

The longest time that an activity might require best defines

(Multiple Choice)
4.8/5
(37)

Identify and describe three dependencies of project activities.

(Essay)
4.8/5
(34)

Each activity can be crashed at least once.

(True/False)
4.8/5
(48)

Which of the following includes activities performed more quickly than they normally would be performed?

(Multiple Choice)
4.8/5
(37)

For an activity,assume the early start is 3 weeks,early finish is 6 weeks,late start is 4 weeks,and late finish is 7 weeks.What is the activity's slack?

(Multiple Choice)
4.8/5
(43)

The amount of time that an activity in a project network can be delayed without causing a delay to subsequent activities or project completion best defines

(Multiple Choice)
4.8/5
(40)

In order to keep the whole project on schedule,the CCPM method requires project personnel to be strict with their start times.

(True/False)
4.8/5
(42)

An overall management philosophy introduced by Goldratt to help organizations continually achieve their goals best describes

(Multiple Choice)
4.8/5
(44)

Capacity measures how early or late an activity can start or finish.

(True/False)
5.0/5
(34)

Basic reasons for creating dependencies of project activities include each of the followingexcept

(Multiple Choice)
4.8/5
(34)

What is negative slack? Why does it occur?

(Essay)
4.8/5
(37)

For an activity,assume the early start is 12,early finish is 27,late start is 19,and late finish is 34.What is the activity's slack?

(Multiple Choice)
4.7/5
(33)

When constructing the PDM,an activity can have

(Multiple Choice)
4.9/5
(36)

Causing a delay to the whole project is called free float.

(True/False)
4.7/5
(38)

SAP PS is a free,web-based project software package.

(True/False)
4.8/5
(39)

Popular project management software packages include each of the following except

(Multiple Choice)
4.9/5
(38)

Negative slack can occur due to

(Multiple Choice)
4.9/5
(35)

A work breakdown flowchart is useful for all stakeholders to track the project from beginning to finish.

(True/False)
4.9/5
(41)

If the early start for an activity is 7 and the late start is 12,then the activity's slack is 84.

(True/False)
4.7/5
(42)
Showing 61 - 80 of 80
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)