Exam 8: Project Scheduling
Exam 1: Projects and Project Management80 Questions
Exam 2: Process and Methods80 Questions
Exam 3: Project Management Tools80 Questions
Exam 4: Project Initiation80 Questions
Exam 5: Project Planning80 Questions
Exam 6: Risk Management80 Questions
Exam 7: Quality, Performance and Value80 Questions
Exam 8: Project Scheduling80 Questions
Exam 9: Resources, Costing, and Control80 Questions
Exam 10: Project Closure80 Questions
Exam 11: Project Organizational Structures80 Questions
Exam 12: Project Success80 Questions
Select questions type
The longest time that an activity might require best defines
(Multiple Choice)
4.8/5
(37)
Which of the following includes activities performed more quickly than they normally would be performed?
(Multiple Choice)
4.8/5
(37)
For an activity,assume the early start is 3 weeks,early finish is 6 weeks,late start is 4 weeks,and late finish is 7 weeks.What is the activity's slack?
(Multiple Choice)
4.8/5
(43)
The amount of time that an activity in a project network can be delayed without causing a delay to subsequent activities or project completion best defines
(Multiple Choice)
4.8/5
(40)
In order to keep the whole project on schedule,the CCPM method requires project personnel to be strict with their start times.
(True/False)
4.8/5
(42)
An overall management philosophy introduced by Goldratt to help organizations continually achieve their goals best describes
(Multiple Choice)
4.8/5
(44)
Capacity measures how early or late an activity can start or finish.
(True/False)
5.0/5
(34)
Basic reasons for creating dependencies of project activities include each of the followingexcept
(Multiple Choice)
4.8/5
(34)
For an activity,assume the early start is 12,early finish is 27,late start is 19,and late finish is 34.What is the activity's slack?
(Multiple Choice)
4.7/5
(33)
Popular project management software packages include each of the following except
(Multiple Choice)
4.9/5
(38)
A work breakdown flowchart is useful for all stakeholders to track the project from beginning to finish.
(True/False)
4.9/5
(41)
If the early start for an activity is 7 and the late start is 12,then the activity's slack is 84.
(True/False)
4.7/5
(42)
Showing 61 - 80 of 80
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)