Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Agile Project Management is well-suited for instances where:
(Multiple Choice)
4.9/5
(38)
Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.A feeder buffer should be placed immediately before: Activity Predecessor Length Resource Activity Predecessor Length Resource A - 11 P D C 13 P B A 7 M E - 12 8 14
(Multiple Choice)
4.8/5
(39)
The waterfall project development process is well-suited for instances where:
(Multiple Choice)
4.9/5
(34)
A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration? Standard Activity Predecessor Length Deviation A - 10 2 B A 12 3 C A 16 2 D B,C 14 3
(Multiple Choice)
4.9/5
(39)
Keith welds a one-fourth-inch diameter ball bearing and a three-eighths-inch diameter ball bearing on each end of an eighth-inch diameter cylinder.Sure,the work is tedious,but he knows he's doing his part keeping this country running and lining his employer's pockets with sweet cash.His employer hopes to speed up this activity by hiring another skilled worker,and in doing so will:
(Multiple Choice)
4.8/5
(44)
Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.The critical chain does NOT pass through: Activity Predecessor Length Resource Activity Predecessor Length Resource A - 11 P D C 13 P B A 7 M E - 12 8 14
(Multiple Choice)
4.8/5
(38)
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology? Activity Predecessor Lengenth Activity Predecessor Length A -- 18 , 13 B - 16 9 22 , 15 14
(Multiple Choice)
4.8/5
(33)
What is aggregated buffer and how can the appropriate amount be determined?
(Essay)
5.0/5
(38)
An important departure from traditional project management is that critical chain project management logic:
(Multiple Choice)
4.8/5
(38)
A project consists of four activities with information as shown in the table.What is the overall standard deviation of the project? Activity Predecessor Length Variance -- 10 4 12 3 16 5 14 6
(Multiple Choice)
4.8/5
(30)
The legal department is needed to review all contracts a project organization enters.The legal department is continually swamped with work and all other departments find themselves waiting on legal before they can begin their work.Legal is the drum for this organization.
(True/False)
4.7/5
(37)
A feeder buffer is a buffer that is created for a non-critical path activity.
(True/False)
4.9/5
(29)
What are the five steps behind the Theory of Constraints methodology and what takes place in each?
(Essay)
4.8/5
(27)
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Newbold's model to determine the aggregated one sigma buffer for this project. Activity Average Worst-Case 10 20 15 25 20 30 25 35
(Multiple Choice)
4.8/5
(34)
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology? Activity Predecessor Lengenth Activity Predecessor Length A -- 18 , 13 B - 16 9 22 , 15 14
(Multiple Choice)
4.9/5
(46)
When choosing the most viable solution to resource conflict issues,the BEST option is the one that:
(Multiple Choice)
4.8/5
(26)
A key to successful project management is ________ leadership.
(Multiple Choice)
4.9/5
(33)