Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length - 8 -- 12 - 8 14 12 , 7 10 , 11
(Multiple Choice)
4.8/5
(44)
Wayne and Garth are engaged in XP and are constantly streamlining the design and improving the code.In XP terminology,they are engaged in:
(Multiple Choice)
4.8/5
(35)
Agile project management features a logical series of steps that occur sequentially,each one is begun only when its predecessor is complete.
(True/False)
4.9/5
(40)
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Lengenth Activity Predecessor Length A -- 18 , 13 B - 16 9 22 , 15 14
(Multiple Choice)
4.8/5
(30)
A project that consists of six consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.How does the project buffer computed this way compare with the estimation for project buffer offered by Goldratt?
Activity Average Worst-Case A 14 21 B 20 28 16 23 8 15 E 9 19
(Essay)
4.8/5
(46)
Which of the following statements about CCPM activity networks is CORRECT?
(Multiple Choice)
4.8/5
(36)
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project. Activity Average Worst-Case 12 20 20 25 14 24 18 26
(Multiple Choice)
4.8/5
(36)
Your next project consists of 8 consecutive 8-day activities,each estimated by a different worker in your organization.Your organizational culture dictates that you add your own safety margin of 3 days into your estimates.Unbeknownst to you,the project manager has recently converted to a critical chain project management view.The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place.What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule?
(Multiple Choice)
4.9/5
(41)
Your next project consists of 10 consecutive 8-day activities,each estimated by a different worker in your organization.Note that the estimators have not yet added any buffer to the 8-day figure.Your organizational culture dictates that you add your own safety margin of 30% into your estimates.The new project manager has just completed an excellent course in project management offered at the local university.When the first project meeting begins,he dazzles you with his wit and sophistication.You are considerably less charmed when he reveals that he has an exciting new technique for managing projects.He adheres to critical chain project management ideas and plans to create an overall project safety buffer after trimming the safety buffers from each of the 10 activities.How much closer has the project deadline moved?
(Multiple Choice)
4.9/5
(32)
The one element that Agile shares with traditional project management in a software development environment is that all testing is done at the very end of the project.
(True/False)
4.9/5
(35)
Which statement about critical chain project management is BEST?
(Multiple Choice)
4.9/5
(31)
Picture yourself as a project manager intent on bringing CCPM to your organization that has historically used classic critical path project management.How would you convince your project team to develop 50% estimates for their project contributions rather than the 90% estimates they have used since they started with the company?
(Essay)
4.8/5
(25)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length - 8 -- 12 - 8 14 12 , 7 10 , 11
(Multiple Choice)
4.9/5
(39)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology? Activity Predecessor Ieength Activity Predecesser Ieength A -- 20 16 A 20 8 A 10 , 8
(Multiple Choice)
4.8/5
(35)
In order to resolve a resource conflict,it is advisable to:
(Multiple Choice)
4.7/5
(36)
Showing 41 - 60 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)