Exam 16: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The theory of constraints has a goal of maximizing flow through the entire system.

(True/False)
4.7/5
(49)

If he uses the first come, first served (FCFS) priority rule to schedule these jobs, what will be the average completion time?

(Multiple Choice)
4.8/5
(39)

What is the result of the row reduction?

(Essay)
4.8/5
(32)

Job X, which has a duration of four days, is due by the close of business on Friday, December 23.Without looking at the work already at X's required resource, the scheduler schedules X to be begun immediately and assumes that X will be done four days from now.This is an example of ___________.

(Multiple Choice)
4.9/5
(33)

What is the schedule sequence using the earliest due date (EDD) priority rule?

(Short Answer)
4.8/5
(41)

A major disadvantage of the SPT rule is that it tends to make very short jobs wait for a long time while longer, more important jobs are processed.

(True/False)
4.8/5
(36)

What is the schedule sequence using the first come, first served (FCFS) priority rule?

(Short Answer)
4.8/5
(38)

Infinite loading and finite loading are two major approaches used to load work centers.

(True/False)
4.8/5
(40)

A scheduling technique used to achieve an optimum, one-to-one matching of tasks and resources is:

(Multiple Choice)
4.8/5
(39)

The costs to do each of the three jobs on three alternate pieces of equipment are given below.Determine the job-equipment combination that will minimize total cost.

(Essay)
4.9/5
(30)

Where in the optimum sequence should car A be scheduled?

(Multiple Choice)
4.8/5
(38)

A work center can be a ___________.

(Multiple Choice)
4.9/5
(37)

Makespan is the total time needed to complete a group of jobs.

(True/False)
4.9/5
(35)

The assignment model seeks an optimum matching of tasks and resources.

(True/False)
4.9/5
(29)

Scheduling in service systems often takes the form of:

(Multiple Choice)
4.8/5
(36)

Priority rules are used in low-volume systems to identify an optimal processing sequence.

(True/False)
4.7/5
(39)

Which of the following is not usually a characteristic of successful high-volume systems?

(Multiple Choice)
4.7/5
(27)

When operations are often bottlenecked, additional planned idle time will improve the throughput in those areas.

(True/False)
4.9/5
(32)

Scheduling in intermediate-volume systems has three basic issues: run size, timing, and sequence.

(True/False)
5.0/5
(39)

As long as the bottleneck operations are used effectively idle time in non-bottleneck operations will not affect the overall productivity of the system.

(True/False)
4.8/5
(43)
Showing 61 - 80 of 134
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)