Exam 16: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If optimal sequencing through three work centers is desired, Johnson's Rule II is used rather than Johnson's Rule.

(True/False)
4.7/5
(32)

A Gantt chart is a basic scheduling tool that is most useful in low-volume systems.

(True/False)
4.8/5
(42)

If these jobs were scheduled in the sequence shown, what would be the throughput time?

(Short Answer)
4.7/5
(38)

If he uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?

(Multiple Choice)
4.9/5
(37)

Which of the following is not a measure for judging the effectiveness of a schedule sequence?

(Multiple Choice)
4.9/5
(41)

A basic difference between scheduling in service systems and scheduling in manufacturing systems is the random nature of requests in manufacturing systems as opposed to more uniform requests in service systems.

(True/False)
4.8/5
(41)

The priority rule where jobs are processed according to the smallest ratio of due date to processing time is:

(Multiple Choice)
4.9/5
(42)

Splitting a large lot after one operation beyond a bottleneck operation would reduce the overall waiting time of the bottleneck operation.

(True/False)
4.9/5
(36)

Which of the following is not an example of a high-volume system?

(Multiple Choice)
4.8/5
(24)

Average completion (flow) time for a schedule sequence at a work center is:

(Multiple Choice)
4.8/5
(36)

Given the following information concerning jobs awaiting processing at a single work center, what processing sequence will result if the critical ratio (C/R) rule is used?

(Essay)
4.8/5
(44)

What is the optimal assignment of resources to jobs?

(Multiple Choice)
4.9/5
(41)

Job X, which has a duration of four days, is due by the close of business on Friday, December 23.Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20.This is an example of __________.

(Multiple Choice)
4.8/5
(42)

After the row and column reductions, what is the reduced time for assigning Rick to project D?

(Multiple Choice)
4.7/5
(25)

The quantity sent to a bottleneck operation could be split into two or more process batches to better utilize a bottleneck resource rather than process the entire batch.

(True/False)
5.0/5
(34)

If jobs A, B, and C require two operations each, while jobs D and E require one operation each, what is the schedule sequence using the slack per operation (S/O) priority rule?

(Short Answer)
4.8/5
(32)

In how many different ways can she assign these consultants to these projects?

(Multiple Choice)
4.9/5
(36)

In developing the sequence that will minimize throughput time, where in the schedule sequence should job W be placed?

(Short Answer)
4.9/5
(25)

When orders exceed our capacity, priority rules are used to select which orders will be accepted.

(True/False)
4.8/5
(41)

In developing the sequence which will minimize throughput time, what is the initial job to be placed in the schedule sequence?

(Short Answer)
4.9/5
(37)