Exam 16: Scheduling
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
For the jobs listed below, which processing sequence would result using Johnson's Rule? 

(Multiple Choice)
4.9/5
(29)
A Gantt chart is a basic scheduling tool but works best for high-volume systems.
(True/False)
4.7/5
(36)
The output of the system cannot exceed the output of the bottleneck operation(s).
(True/False)
4.8/5
(37)
Determine the processing sequence for the six jobs shown below using Johnson's Rule.Calculate total throughput time.Can the makespan be reduced by splitting the latest job? If so, by how much?
(Essay)
4.9/5
(42)
The elimination of idle time on both bottleneck and non-bottleneck operations must be accomplished to optimize output.
(True/False)
4.7/5
(39)
What are the total costs for the optimum assignment of jobs to machines?
(Short Answer)
4.9/5
(34)
Based on the cost information given in the table below, which set of job-machine pairs reflects the minimum-cost solution using the Assignment method? 

(Multiple Choice)
4.8/5
(38)
If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in her shop today?
(Multiple Choice)
4.9/5
(36)
After the row reduction, what is the reduced time for assigning resource 4 to Job D?
(Multiple Choice)
4.7/5
(36)
If these jobs were scheduled in the sequence shown, what would be the idle time at machine B?
(Short Answer)
4.9/5
(42)
If Eva uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?
(Multiple Choice)
4.9/5
(40)
After the row and column reductions, what is the minimum number of lines needed to cover all of the zeroes?
(Multiple Choice)
4.9/5
(40)
The term loading, as used in scheduling, refers to choosing the order in which jobs will be processed in low-volume systems.
(True/False)
4.8/5
(31)
If these jobs were scheduled in the sequence shown, when would idle time occur at machine B?
(Short Answer)
4.9/5
(29)
In the decision-making hierarchy, scheduling decisions are the final step in the transformation process before actual output occurs.
(True/False)
5.0/5
(30)
Showing 41 - 60 of 134