Exam 16: Scheduling
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
Which of the following is critical to effective yield management?
(Multiple Choice)
4.8/5
(31)
What is the average completion time for the first come, first served (FCFS) priority rule schedule? Average job tardiness? Average number of jobs at the center?
(Short Answer)
4.8/5
(36)
Input/output (I/O) control refers to monitoring the productivity changes since productivity is determined by the ratio of Output to Input.
(True/False)
4.8/5
(34)
After the row and column reductions, what is the reduced time for assigning resource 4 to job D?
(Multiple Choice)
4.7/5
(50)
Which of the following is least likely to be a consideration when scheduling a high-volume system?
(Multiple Choice)
4.9/5
(33)
What is the average completion time for the slack per operation (S/O) priority rule schedule? Average job tardiness? Average number of jobs at the center?
(Short Answer)
4.8/5
(36)
A schedule chart depicts the loading and idle times for a group of machines or departments.
(True/False)
4.8/5
(35)
Which of the following is the last step in the capacity/scheduling chain?
(Multiple Choice)
4.8/5
(36)
If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?
(Multiple Choice)
4.8/5
(43)
Sequencing is concerned with the order in which jobs are done, while loading is concerned with assigning jobs to work centers or workstations.
(True/False)
4.8/5
(44)
The EDD priority rule usually does well with regard to _______.
(Multiple Choice)
4.9/5
(39)
If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average job tardiness?
(Multiple Choice)
4.9/5
(34)
Which sequencing rule is designed specifically to minimize job tardiness?
(Multiple Choice)
4.9/5
(34)
The SPT priority rule always results in the lowest average completion time.
(True/False)
4.8/5
(36)
Which of the following is not an assumption of priority rules?
(Multiple Choice)
4.9/5
(43)
Use Johnson's Rule to determine the optimum processing sequence for the jobs listed below.Chart total throughput time.
(Essay)
4.8/5
(38)