Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When a project manager must reduce project duration but resources are constrained,creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of

(Multiple Choice)
4.9/5
(45)

An activity must be crashed on each critical path in order to reduce project duration.

(True/False)
4.8/5
(35)

An activity's normal time and cost are 5 and $40,respectively.Its estimated crash time and cost are 4 and $70,respectively.This activity's crash cost per time unit is ________.

(Short Answer)
4.8/5
(40)

How would you calculate an activity's slope and what does it represent?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

(Multiple Choice)
4.8/5
(40)

Direct costs are assignable directly to a particular ________.

(Short Answer)
4.9/5
(46)

Crashing frequently results in overallocation of resources.

(True/False)
4.9/5
(29)

One of the advantages of using a Project Cost-Duration Graph is that it keeps the importance of indirect costs in the forefront of decision making.

(True/False)
4.7/5
(37)

Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.

(True/False)
4.8/5
(38)

A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by

(Multiple Choice)
4.9/5
(42)

The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.

(Multiple Choice)
4.8/5
(31)

Reducing project duration

(Multiple Choice)
4.8/5
(38)

Without any formal planning,the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by

(Multiple Choice)
4.8/5
(48)

The cost slope of an activity is calculated by dividing the run by the rise.

(True/False)
5.0/5
(33)

If indirect costs are a significant percentage of total project costs,reductions in project time can represent very real savings.

(True/False)
4.9/5
(36)

Why is the project duration with the lowest direct costs seldom the optimum duration for a project?

(Not Answered)
This question doesn't have any answer yet
Ask our community

When project managers know an activity's ________,they are able to compare which critical activities to shorten.

(Short Answer)
4.8/5
(30)

According to ________ law,adding more manpower to a late software project makes it later.

(Short Answer)
4.8/5
(37)

Which of the following correctly calculates an activity's cost slope?

(Multiple Choice)
4.7/5
(41)

All of the following are disadvantages of scheduling overtime EXCEPT

(Multiple Choice)
4.7/5
(37)
Showing 21 - 40 of 94