Exam 9: Reducing Project Duration
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
The ________ project cost is the sum of the indirect and direct costs.
(Short Answer)
4.8/5
(45)
The shortest possible time an activity can be completed realistically is called ________ time.
(Multiple Choice)
4.8/5
(40)
When determining which activity to crash,there are other factors that should be assessed beyond cost.Which of the following is NOT one of these factors?
(Multiple Choice)
4.8/5
(35)
Which of the following projects would be least benefited if additional resources were added?
(Multiple Choice)
4.9/5
(30)
As a project is crashed and project duration is reduced,indirect costs typically
(Multiple Choice)
4.9/5
(41)
When considering whether to move the project to its optimum cost-time position,the manager should also consider ________.
(Short Answer)
4.9/5
(36)
The easiest way to add more labor to a project is not to add more people,but to schedule overtime.What are the disadvantages of scheduling overtime?
(Not Answered)
This question doesn't have any answer yet
____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
(Short Answer)
4.7/5
(35)
One way of reducing project costs is identifying tasks that _________ can do themselves.
(Multiple Choice)
4.8/5
(41)
The total cost for each time unit of a project is the sum of labor,materials,and equipment.
(True/False)
4.8/5
(40)
When do you know you have crashed project activities enough? In other words,when you are crashing a project,how do you know you are finished?
(Not Answered)
This question doesn't have any answer yet
Indirect costs generally represent overhead costs such as supervision,administration,consultants,and interest.