Exam 20: Constraint Management
Exam 1: Introduction to the Field59 Questions
Exam 2: Operations and Supply Strategy61 Questions
Exam 3: Project Management95 Questions
Exam 4: Product and Service Design53 Questions
Exam 5: Strategic Capacity Management52 Questions
Exam 6: Process Analysis50 Questions
Exam 7: Manufacturing Processes42 Questions
Exam 8: Service Processes59 Questions
Exam 9: Six Sigma Quality83 Questions
Exam 10: Supply-Chain Strategy67 Questions
Exam 11: Logistics and Facility Location56 Questions
Exam 12: Lean Manufacturing74 Questions
Exam 13: Operations Consulting Reengineering68 Questions
Exam 14: Enterprise Resource Planning Systems35 Questions
Exam 15: Demand Management and Forecasting105 Questions
Exam 16: Aggregate Sales and Operations Planning64 Questions
Exam 17: Inventory Control100 Questions
Exam 18: Material Requirements Planning111 Questions
Exam 19: Scheduling69 Questions
Exam 20: Constraint Management64 Questions
Exam 21: Linear Programming Using the Excel Solver40 Questions
Exam 22: Learning Curves57 Questions
Exam 23: Job Design Work Measurement61 Questions
Exam 24: Waiting Line Analysis61 Questions
Exam 25: Process Capability and Spc75 Questions
Exam 26: Simulation54 Questions
Select questions type
Larger transfer batches give shorter lead times and lower inventories and there is more material handling than smaller transfer batches.
Free
(True/False)
4.9/5
(40)
Correct Answer:
False
You have run a capacity resource profile on your shop.Products have been routed sequentially through resources A,B,C & D.The capacity resource profile tells you that recourse A is scheduled at 95 percent of capacity,recourse B at 80% of capacity,recourse C at 130% of capacity and recourse D at 100% of capacity.Assuming that the data we used to calculate the capacity resource profile was reasonably accurate,what would we expect to find when we go out to the shop?
Free
(Short Answer)
4.8/5
(27)
Correct Answer:
A large quantity of work-in-process inventory in front of resource C.
What are the three financial measures of the firm's ability to make money?
Free
(Short Answer)
4.8/5
(44)
Correct Answer:
1.Net profit
2.Return on investment
3.Cash flow
According to the theory of constraints,a capacity-constrained resource (CCR)is one whose utilization is close to capacity and could be a bottleneck if it is not scheduled carefully.
(True/False)
4.9/5
(40)
The operational measure of throughput is "the rate at which money is generated by the system through production of goods and services that might be sold".
(True/False)
4.9/5
(36)
Departments within a firm often are at odds with each other because reward systems are often not synchronized with the basic goal of the firm: to make money.
(True/False)
4.8/5
(35)
An MRP system can allow for product rejects by building a larger batch than is demanded,but a JIT system cannot tolerate poor quality.
(True/False)
4.9/5
(43)
The "dollar days" inventory measurement results from a complex algorithm used to compute individual units of inventory and their respective ordering and holding costs.
(True/False)
4.8/5
(30)
You have run a capacity resource profile on your shop.Products have been routed sequentially through resources A,B,C &D.The capacity resource profile tells you that recourse A is scheduled at 95 percent of capacity,recourse B at 80% of capacity,recourse C at 130% of capacity and recourse D at 100% of capacity.Assuming that the data we used to calculate the capacity resource profile was reasonably accurate,what have we discovered about the process A,B,C & D?
(Short Answer)
4.8/5
(42)
JIT requires work-in-process when used with kanban so there is inventory to pull.When compared to synchronous manufacturing this is viewed as a negative aspect of JIT.
(True/False)
4.9/5
(29)
JIT requires a stable production Level.When compared to synchronous manufacturing this is viewed as a negative aspect of JIT.
(True/False)
4.8/5
(41)
According to the theory of constraints which of the following is an operational measurement that can be used to measure the firm's ability to make money?
(Multiple Choice)
4.9/5
(41)
In discussing batch size on an assembly line the text makes the point that "one" and "infinity" are equally correct Answers.How can this be?
(Essay)
4.8/5
(36)
A way to find a bottleneck is to use one's knowledge of a particular plant,look at the system in operation and talk with supervisors and workers.
(True/False)
4.8/5
(43)
A synchronous manufacturing system does not have excess capacity throughout the system,except for a bottleneck.
(True/False)
4.8/5
(45)
Which of the following is an approach to dealing with a bottleneck?
(Multiple Choice)
4.7/5
(36)
Showing 1 - 20 of 64
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)