Exam 22: Learning Curves
Exam 1: Introduction to the Field59 Questions
Exam 2: Operations and Supply Strategy61 Questions
Exam 3: Project Management95 Questions
Exam 4: Product and Service Design53 Questions
Exam 5: Strategic Capacity Management52 Questions
Exam 6: Process Analysis50 Questions
Exam 7: Manufacturing Processes42 Questions
Exam 8: Service Processes59 Questions
Exam 9: Six Sigma Quality83 Questions
Exam 10: Supply-Chain Strategy67 Questions
Exam 11: Logistics and Facility Location56 Questions
Exam 12: Lean Manufacturing74 Questions
Exam 13: Operations Consulting Reengineering68 Questions
Exam 14: Enterprise Resource Planning Systems35 Questions
Exam 15: Demand Management and Forecasting105 Questions
Exam 16: Aggregate Sales and Operations Planning64 Questions
Exam 17: Inventory Control100 Questions
Exam 18: Material Requirements Planning111 Questions
Exam 19: Scheduling69 Questions
Exam 20: Constraint Management64 Questions
Exam 21: Linear Programming Using the Excel Solver40 Questions
Exam 22: Learning Curves57 Questions
Exam 23: Job Design Work Measurement61 Questions
Exam 24: Waiting Line Analysis61 Questions
Exam 25: Process Capability and Spc75 Questions
Exam 26: Simulation54 Questions
Select questions type
A learning curve is a line displaying the way unit production time decreases as time passes.
Free
(True/False)
4.9/5
(40)
Correct Answer:
False
You have determined that a 60 percent learning curve is appropriate for a task.If your initial timing of person performing that task was 35 minutes and if you need the task performed 1,000 times,how many minutes of work will be required?
Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
C
The 15th repetition of a job is timed at 100 minutes.If the learning curve for this job is 90 percent,what is the estimated time for the 120th repetition of this job?
Free
(Short Answer)
4.9/5
(41)
Correct Answer:
72.9 minutes
If a person performing a task has been achieving a 75 percent learning curve and you know that the task will end after the 80th unit,the last unit produced will take 17.12 percent as much time as the first unit.
(True/False)
4.9/5
(44)
An assumption of learning curve theory is which of the following?
(Multiple Choice)
4.9/5
(47)
The unit improvement factor is not as useful as the learning curve statistics in adjusting time estimates for learning.
(True/False)
4.9/5
(39)
An assumption of learning curves is that the time required to complete a unit will decrease at a decreasing rate as the cumulative number of units completed increases.
(True/False)
4.8/5
(39)
Which of the following computational methods are used to calculate learning curve statistics?
(Multiple Choice)
4.8/5
(24)
If a person performing a task has been achieving an 80 percent learning curve and it took 10 minutes to produce the first unit,the total time to produce 100 units will be 326.5 minutes.
(True/False)
4.8/5
(36)
You have just timed a person doing a job a four times.The first time it took the person 120 minutes,the second time it took 90 minutes,the third time it took 76.1 minutes and the fourth time it took 67.5 minutes.Which Learning Curve Unit Improvement Factor should you use?
(Multiple Choice)
4.8/5
(44)
You time someone completing a single task the first time at 10 minutes and the second time they do the task it takes 9 minutes.You should use an 80 percent learning curve to estimate the length of time this worker will take to complete this task in the future.
(True/False)
4.9/5
(45)
An assumption of learning curves is that the time required to complete a unit will increase at an increasing rate as the cumulative number of units completed increases.
(True/False)
4.9/5
(36)
The general guidelines provided in the textbook on improving individual learning based on learning curves includes which of the following?
(Multiple Choice)
4.9/5
(43)
A company can produce a small lot of products the first time at a cost of $10,000.If their 75 percent learning curve allows them to reduce their costs on each lot,what is the total cost of producing 10 lots?
(Multiple Choice)
4.9/5
(37)
A company can produce a small lot of products the first time at a cost of $3,000.If their 65 percent Learning Curve allows them to reduce their costs on each lot,what is the cost of producing the 20th lot?
(Multiple Choice)
4.8/5
(37)
A learning curve is a line displaying the relationship between unit production time and the cumulative number of units produced.
(True/False)
4.9/5
(38)
On a learning curve plot,the time per unit is usually displayed on the vertical axis.
(True/False)
4.9/5
(44)
If a person performing a task has been achieving a 95 percent learning curve and you know that the task will end after the 100th unit,the last unit produced will take 71.12 percent as much time as the first unit.
(True/False)
4.8/5
(36)
The 50th repetition of a job is timed at 100 minutes.If the learning curve for this job is 90 percent,what is the estimated time for the 200th repetition of this job?
(Multiple Choice)
4.8/5
(33)
Showing 1 - 20 of 57
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)